Neglected Work by Contractor Sample Clauses

The "Neglected Work by Contractor" clause defines the procedures and remedies available when a contractor fails to perform or complete required work as specified in the contract. Typically, this clause allows the project owner to issue a notice to the contractor identifying the neglected tasks and may grant a specified period for the contractor to correct the deficiencies. If the contractor does not address the neglected work within the given timeframe, the owner may have the right to complete the work themselves or hire another party to do so, often at the contractor’s expense. This clause ensures that project timelines and quality standards are maintained by providing a clear mechanism to address and rectify contractor inaction or substandard performance.
Neglected Work by Contractor. If Contractor should fail to prosecute the Work in accordance with the Contract Documents, including any requirements of the progress schedule, County, after ten (10) days written notice to Contractor may, without prejudice to any other remedy it may have, make good such deficiencies and the cost thereof (including compensation for additional professional services) shall be charged against Contractor in which case a Modification shall be issued incorporating the necessary revisions in the Contract Documents including appropriate reduction in the Contract Sum. If the payments then or thereafter due Contractor are not sufficient to cover such amount, Contractor shall pay the difference to County.
Neglected Work by Contractor. If Contractor should neglect to prosecute the work diligently, including requirements of the Construction Schedule, ITP, after seven (7) days’ Notice to Contractor may, without prejudice to any other remedy that ITP may have, correct, and remedy any such deficiency. Direct and indirect costs of ITP, including compensation for additional engineering services, shall be verified by ITP Project Manager and an appropriate reduction in the Contract Price will be made. If the payments due Contractor are not sufficient to cover such amount, Contractor shall pay the difference to ITP.
Neglected Work by Contractor. 14.8.1 If the Contractor neglects to execute the Work in accordance with the Contract Documents, including any requirements of the progress schedule, the Professional may direct the Contractor to submit a recovery plan and take specific corrective actions including, but not limited to, employing additional workmen, and/or equipment, and working extended hours and additional days, all at no cost to the City in order to put the Work back on schedule. If the Contractor fails to correct the deficiency or take appropriate corrective action, the City may terminate the contract or Contractor’s right to proceed with that portion of Work and have the Work done by others. The cost of completion under such procedure shall be charged against the Contractor. A Change Order shall be issued incorporating the necessary revisions in the Contract Documents, including an appropriate reduction in the Contract Price. If the payments due the Contractor are not sufficient to cover such amount, the Contractor shall pay the difference to the City. 14.8.2 Should the Contractor work overtime, weekends or holidays to regain the schedule, all costs to the City of associated inspection, construction management and resident engineering shall be identified to the Contractor and the Contract Price reduced by a like amount via Change Order.
Neglected Work by Contractor. DRAFT 1. If CONTRACTOR neglects to execute the Work in accordance with the Contract Documents, including any requirements of the progress schedule, PROJECT MANAGER may direct CONTRACTOR to submit a recovery plan and take specific corrective actions including, but not limited to, employing additional workmen and/or equipment, and working extended hours and additional days, all at no cost to AUGUSTA in order to put the Work back on schedule. If CONTRACTOR fails to correct the deficiency or take appropriate corrective action, AUGUSTA may terminate the contract or CONTRACTOR’s right to proceed with that portion of Work and have the Work done by others. The cost of completion under such procedure shall be charged against CONTRACTOR. A Change Order shall be issued incorporating the necessary revisions in the Contract Documents, including an appropriate reduction in the Contract Price. If the payments due CONTRACTOR are not sufficient to cover such amount, CONTRACTOR shall pay the difference to AUGUSTA. 2. Should CONTRACTOR work overtime, weekends or holidays to regain the schedule, all costs to AUGUSTA of associated inspection, construction management and resident engineers shall be identified to CONTRACTOR and the Contract Price reduced by a like amount via Change Order.
Neglected Work by Contractor. If Contractor should neglect to prosecute the Work in accordance with the Agreement, including any requirements of the progress schedule, City, may, without prejudice to any other remedies which it may have, employ such remedies available to it under this Agreement, including those listed in Section 13.02.

Related to Neglected Work by Contractor

  • Claim by Contractor After receipt of the Notice of Termination from the state, the Contractor shall submit any claim for additional costs not covered herein or elsewhere in the Contract within 60 days of the effective termination date, and not thereafter. Should the Contractor fail to submit a claim within the 60-day period, the State may, at its sole discretion, based on information available to it, determine what, if any, compensation is due the Contractor and pay the Contractor the determined amount.

  • Termination by Contractor Contractor may, at its option, terminate this Contract upon the failure of MPS to pay any amount, which may become due hereunder for a period of sixty (60) days following submission of appropriate billing and supporting documentation. Upon said termination, Contractor shall be paid the compensation due for all services rendered through the date of termination including any retainage.

  • Default by Contractor To the maximum extent permitted by applicable law, failure to comply with any of the terms and/or conditions of this Contract, including these General Conditions, shall constitute default by Contractor and grounds for termination of this Contract. Contractor shall be liable for any and all damages suffered by District due to the failure by Contractor or Contractor’s subcontractor(s) to comply with this Contract.

  • By Contractor Should the Contractor be liable for any payments to the State hereunder, interest, late payment charges and collection fee charges will be determined and assessed pursuant to Section 18 of the State Finance Law.

  • Related Work Leave not to exceed one (1) year may be granted to an employee to accept a position of fixed duration outside of State service which is funded by a government or private foundation grant and which is related to the employee's current work.