Non-Compliant Work. Should the AE and/or the ODR identify Work as non-compliant with the Contract Documents, the ODR will communicate the finding to the Contractor and the Contractor will correct such Work at its expense. The approval of Work by either the AE or ODR does not relieve the Contractor from the obligation to comply with all requirements of the Contract Documents.
Appears in 1 contract
Sources: Contract
Non-Compliant Work. Should the AE and/or the ODR identify Work as non-compliant with the Contract Documents, the ODR will communicate the finding to the Contractor CM-at-Risk and the Contractor CM-at-Risk will correct such Work at its expense. The approval of Work by either the AE or ODR does not relieve the Contractor CM-at-Risk from the obligation to comply with all requirements of the Contract Documents.
Appears in 1 contract
Sources: Solicitation Amendment