Non-Material Breach. With respect to a breach of this Agreement that is neither a Material Breach nor a breach of Article 6 (Quality Assurance), a Party may provide the other Party with written notice alleging that the other Party has breached an obligation under the Agreement. The written notice must set forth with particularity a description of the purported breach and requested actions to remedy the breach. The Party accused of breach in such notice will have 30 days from the date of receipt of the notice to cure the breach. If the breach is not capable of being cured within 30 days, the Party accused will have an additional 30 days to cure the breach. The breaching Party shall act in good faith, using commercially reasonable efforts to cure the breach as soon as possible, but not later than 60 days from receipt of the initial notice.
Appears in 3 contracts
Sources: Trademark License Agreement (TimkenSteel Corp), Trademark License Agreement (Timken Co), Trademark License Agreement (TimkenSteel Corp)