Non-Substantive Amendments. 6.1.1 The following items are considered by both parties to be not substantive and may be amended by resolution of Council. (a) Changes to parking as detailed in Section 3.5 which do not conform with Schedule B; (b) Changes to hours of operation as detailed in Section 3.13; (c) Changes to signage as detailed in Section 3.10; (d) The granting of an extension to the date of commencement of construction as identified in Section 7.3 of this Agreement; and (e) The length of time for the completion of the development as identified in Section 7.5 of this Agreement.
Appears in 2 contracts
Sources: Development Agreement, Development Agreement
Non-Substantive Amendments. 6.1.1 The following items are considered by both parties to be not substantive and may be amended by resolution of Council.
(a) Changes to the parking measures as detailed in Section 3.5 which do not conform with Schedule B3.7;
(b) Changes to hours of operation the building siting as detailed in Section 3.133.4 or which, in the opinion of the Development Officer, do not conform with Schedules B or E;
(c) Changes to signage as detailed in Section 3.10;
(d) The granting of an extension to the date of commencement of construction as identified in Section 7.3 of this Agreement; and
(ed) The length of time for the completion of the development as identified in Section 7.5 of this Agreement.
Appears in 2 contracts
Sources: Development Agreement, Development Agreement
Non-Substantive Amendments. 6.1.1 The following items are considered by both parties to be not non substantive and may be amended by resolution of Council.
(a) Changes Minor changes to parking as detailed in Section 3.5 which do not conform with Schedule Bthe exterior materials of the building;
(b) Changes The parking requirement for 52 spaces may be met by reallocating parking spaces from underground parking to hours surface parking subject to the requirements of operation as detailed in Section 3.13sections 3.5 and 3.7 of this Agreement;
(c) Changes to signage as detailed in Section 3.10;
(d) The granting of an extension to the date of commencement of construction as identified in Section 7.3 Subsection 7.3.1 of this Agreement; and
(ed) The length of time for the completion of the development as identified in Section 7.5 7.4 of this Agreement.
Appears in 1 contract
Sources: Development Agreement
Non-Substantive Amendments. 6.1.1 The following items are considered by both parties to be not substantive and may be amended by resolution of Council.:
(a) Changes to parking as detailed in Section 3.5 which do not conform with Schedule B;
(b) Changes to hours of operation as detailed in Section 3.13;
(c) Changes to signage as detailed in Section 3.10;
(d) The granting of an extension to the date of commencement of construction as identified in Section 7.3 of this Agreement; and7.3.1;
(eb) The length of time for the completion of the development as identified in Section 7.5 7.5.1;
(c) Changes to the parking requirements of this AgreementSection 3.7; and
(d) Changes to the sign requirements of Section 3.10.
Appears in 1 contract
Sources: Development Agreement
Non-Substantive Amendments. 6.1.1 The following items are considered by both parties to be not non-substantive and may be amended by resolution of Council.:
(a) Changes to parking as detailed in Section 3.5 which do not conform with Schedule Bthe site landscaping and corresponding changes to the Schedules;
(b) Changes to hours of operation as detailed in Section 3.13the surface parking layout, parking supply, driveway locations and underground parking access and corresponding changes to the schedules;
(c) Changes to signage as detailed in Section 3.10;
(d) The granting of an extension to the date of commencement of construction as identified in Section 7.3 7.3.1 of this Agreement; and
(ed) The length of time for the completion of the development as identified in Section 7.5 7.4.1 of this Agreement.