Common use of Non-Synchronous Generation Clause in Contracts

Non-Synchronous Generation. The power factor design criteria requirements applicable to non-synchronous Generating Facilities shall be as specified in in Appendix G to the LGIA. The Low Voltage Ride-Through Capability requirements applicable to wind and inverter-based Generating Facilities shall be as specified in Appendix G to the LGIA.

Appears in 14 contracts

Sources: Large Generator Interconnection Agreement, Large Generator Interconnection Agreement, Large Generator Interconnection Agreement

Non-Synchronous Generation. The Generating Facilities shall be subject to the power factor design criteria requirements applicable to non-synchronous Generating Facilities shall be as specified in in Appendix G to the LGIA. The Low Voltage Ride-Through Capability requirements applicable to wind Wind and inverter-based Generating Facilities shall be as subject to the Low Voltage Ride-Through Capability requirements specified in Appendix G to the LGIA.

Appears in 4 contracts

Sources: Interconnection Agreement, Interconnection Agreement, Interconnection Agreement

Non-Synchronous Generation. The Generating Facilities shall be subject to the power factor design criteria requirements applicable to non-synchronous Generating Facilities shall be as specified in in Appendix G to the LGIA. The Wind and inverter- based Generating Facilities shall be subject to the Low Voltage Ride-Through Capability requirements applicable to wind and inverter-based Generating Facilities shall be as specified in Appendix G to the LGIA.

Appears in 2 contracts

Sources: Service Agreement, Standard Small Generator Interconnection Agreement (Sgia)

Non-Synchronous Generation. The Generating Facilities shall be subject to the power factor design criteria requirements applicable to non-synchronous Generating Facilities shall be as specified in in Appendix G to the LGIA. The Low Voltage Ride-Through Capability requirements applicable to wind Wind and inverter-based Generating Facilities shall be as subject to the Low Voltage Ride- Through Capability requirements specified in Appendix G to the LGIA.

Appears in 1 contract

Sources: Small Generator Interconnection Agreement