Notice of Modifications to WSCC Reliability Criteria Agreement. If, following the process specified in Section 4.2, any modification to the WSCC Reliability Criteria Agreement is to take effect, the Transmission Operator shall provide notice to the Generator at least forty-five (45) days before such modification is scheduled to take effect.
Appears in 36 contracts
Sources: Small Generator Interconnection Agreement (Sgia), Standard Large Generator Interconnection Agreement, Small Generator Interconnection Agreement (Sgia)
Notice of Modifications to WSCC Reliability Criteria Agreement. If, following the process specified in Section 4.2, any modification to the WSCC 6 Reliability Criteria Agreement is to take effect, the Transmission Operator shall provide notice to the Generator at least forty-five (45) days before such 7 modification is scheduled to take effect.
Appears in 2 contracts
Sources: Service Agreement, Interconnection Agreement