Notice of Substantial Completion. In the first instance, specified in paragraph 21.9 Modification of Article 6, liquidated damages, if any, shall be the amount specified therein, for each calendar day of delay beginning after the stipulated number of days for Substantial Completion from the date of the Notice to Proceed to Commence Construction Phase, until the date of the Notice of Substantial Completion. Unless otherwise specified in any Supplementary General Conditions, in the event of any partial Notice of Substantial Completion, liquidated damages shall accrue until all required Notices of Substantial Completion are issued.
Appears in 3 contracts
Sources: Construction Manager/General Contractor Agreement, Construction Manager/General Contractor Agreement, Construction Manager/General Contractor Agreement