Notification of Change in Law. 12.3.1 In case any increase or decrease in the Project Cost occurs due to Change in Law affecting the Tariff payable under this Agreement, in accordance with Article 12, the BESSD shall serve notice to SECI and Buying Entity(ies) of such Change in Law for giving a three weeks prior notice about the proposed impact in tariff, positive or negative, to be recovered. BESSD, within thirty days of the occurrence of the change in law or on the expiry of three weeks from the date of the aforementioned notice referred whichever is later, shall furnish SECI and Buying Entity(ies), the computation of impact in tariff or charges to be adjusted and recovered. Such recovery and adjustment of the proposed impact in tariff or charges shall start from the next billing cycle of the tariff. 12.3.2 Any notice service pursuant to this Article 12, shall provide, amongst other things, precise details of the Change in Law and its effect on the Project Cost and computation of change in Tariff which shall be supported by documentary evidences including Statutory Auditor Certificate to this effect so as to establish one to one correlation and its impact on the Project Cost.
Appears in 2 contracts
Sources: Battery Energy Storage Purchase Agreement, Battery Energy Storage Purchase Agreement
Notification of Change in Law. 12.3.1 In case any increase or decrease in the Project Cost occurs due to Change in Law affecting the Tariff payable under this Agreement, in accordance with Article 12, the BESSD SPD shall serve notice to SECI SJVN and Buying Entity(ies) of such Change in Law for giving a three weeks prior notice about the proposed impact in tariff, positive or negative, to be recovered. BESSDSPD, within thirty days of the occurrence of the change in law or on the expiry of three weeks from the date of the aforementioned notice referred whichever is later, shall furnish SECI SJVN and Buying Entity(ies), the computation of impact in tariff or charges to be adjusted and recovered. Such recovery and adjustment of the proposed impact in tariff or charges shall start from the next billing cycle of the tariff.
12.3.2 Any notice service pursuant to this Article 12, shall provide, amongst other things, precise details of the Change in Law and its effect on the Project Cost and computation of change in Tariff which shall be supported by documentary evidences including Statutory Auditor Certificate to this effect so as to establish one to one correlation and its impact on the Project Cost.
Appears in 1 contract
Sources: Power Purchase Agreement