Notification of Delay. If either Party shall have reason to believe that it is being delayed or will be delayed in carrying out the Contestable Components or Essential Component Works for any reason (whether it is one entitling it to the fixing of a new date under Paragraph 03 or not) it shall notify the other Party in writing within five
Appears in 2 contracts
Sources: Connection Agreement, Connection Agreement
Notification of Delay. If either Party shall have reason to believe that it is being delayed or will be delayed in carrying out the Contestable Components or Essential Component Works for any reason (whether it is one entitling it to the fixing of a new date under Paragraph 03 0 or not) it shall notify the other Party in writing within five