Notify Contractor. If clause Reason for Step-In applies and the Authority wishes to take action, the Authority shall notify the Contractor in writing of the following: 56.2.1 the action it wishes to take; 56.2.2 the reason for such action; 56.2.3 the date it wishes to commence such action; 56.2.4 the time period which it believes will be necessary for such action; and 56.2.5 to the extent practicable, the effect on the Contractor and its obligation to provide the Services during the period such action is being taken.
Appears in 1 contract
Sources: Project Agreement
Notify Contractor. If either of the conditions in clause Reason for Step-In 47.1 applies and the Authority wishes to take action, the Authority shall notify the Contractor in writing (“the Step-In Notice”) of the following:following:-
56.2.1 47.2.1 the action it wishes to take;
56.2.2 47.2.2 the reason for such action;
56.2.3 47.2.3 the date it wishes to commence such action;
56.2.4 47.2.4 the time period which it believes will be necessary for such action; and
56.2.5 47.2.5 to the extent practicable, the effect on the Contractor and its obligation to provide the Services during the period such action is being taken.
Appears in 1 contract
Sources: Project Agreement
Notify Contractor. If clause Reason for Step-In Clause 58.1 applies and the Authority wishes to take action, the Authority shall notify the Contractor in writing of the following:
56.2.1 58.2.1 the action it wishes to take;
56.2.2 58.2.2 the reason for such action;
56.2.3 58.2.3 the date it wishes to commence such action;
56.2.4 58.2.4 the time period which it believes will be necessary for such action; and
56.2.5 58.2.5 to the extent practicable, the effect on the Contractor and its obligation to provide the Services during the period such action is being taken.
Appears in 1 contract
Sources: Project Agreement