Common use of Obligation to Notify Owner of Existing Hazardous Materials Clause in Contracts

Obligation to Notify Owner of Existing Hazardous Materials. The Contractor shall immediately notify the Owner and the Design Professional, both orally and in writing, of the presence and location of any physical evidence of, or information regarding the presence of Hazardous Materials at the Site of which it becomes aware. If the Contractor encounters Hazardous Materials on the Site the Contractor shall (i) immediately stop performance of Work or that portion of the Work affected by or affecting such Hazardous Materials; (ii) secure the contaminated area against intrusion;

Appears in 2 contracts

Sources: Design Bid Build Construction Contract, Design Bid Build Construction Contract