Obligations prior to commencement of construction. 12.1.1 The Concessionaire shall furnish to the Independent Engineer, a detailed project report comprising final alignment, details of longitudinal sections, bridges, tunnels, structures and buildings (the “Detailed Project Report or DPR”) in conformity with Specifications and Standards and inter-operability with existing EDFC and Zonal Railway within 180 (one hundred and eighty) days from the date of signing of Concession Agreement. 12.1.2 Prior to commencement of Construction Works, the Concessionaire shall: (a) submit to the Authority and the Independent Engineer its detailed design, construction methodology, quality assurance procedures, and the procurement, engineering and construction time schedule for completion of the Project in accordance with the Project Completion Schedule as set forth in Schedule-D; DRAFT (b) appoint its representative duly authorized to deal with the Authority in respect of all matters under or arising out of or relating to this Concession Agreement; (c) undertake, do and perform all such acts, deeds and things as may be necessary or required before commencement of construction under and in accordance with this Concession Agreement, the Applicable Laws and Applicable Permits; and (d) make its own arrangements for quarrying of materials needed for the Project under and in accordance with the Applicable Laws and Applicable Permits. 12.1.3 Within 30 (thirty) days of the receipt of the DPR, the Independent Engineer shall review the same and convey its observations, if any to the Concessionaire. 12.1.4 In the event that any modifications to the DPR shall have been determined under and in accordance with Clause 12.1.3, the DPR shall be deemed to be modified to the extent thereof.
Appears in 1 contract
Sources: Concession Agreement
Obligations prior to commencement of construction. 12.1.1 The Concessionaire shall furnish to the Independent Engineer, a detailed project report comprising final alignment, details of longitudinal sections, bridges, tunnels, structures and buildings 11.1.1 Within 20 (the “Detailed Project Report or DPR”) in conformity with Specifications and Standards and inter-operability with existing EDFC and Zonal Railway within 180 (one hundred and eightytwenty) days from of the date of signing of Concession Agreement.
12.1.2 Prior to commencement of Construction WorksAppointed Date, the Concessionaire shall:
(a) submit to the Authority and the Independent Engineer its detailed design, construction methodology, quality assurance procedures, and the procurement, engineering and construction time schedule for completion of the Project in accordance with the Project Completion Schedule as set forth in Schedule-D; DRAFT
(b) appoint its representative duly authorized authorised to deal with the Authority in respect of all matters under or arising out of or relating to this Concession Agreement;
(b) appoint a design director (the “Design Director”) who will head the Concessionaire’s design unit and shall be responsible for surveys, investigations, collection of data, and preparation of preliminary and detailed designs;
(c) undertake, do and perform all such acts, deeds and things as may be necessary or required before commencement of construction under and in accordance with this Concession Agreement, the Applicable Laws and Applicable Permits; and
(d) make its own arrangements for quarrying and procurement of materials needed for the Project under and in accordance with the Applicable Laws and Applicable Permits.
12.1.3 11.1.2 The Authority shall, within 15 (fifteen) days of the date of this Agreement, appoint a railway engineer (the “Authority’s Engineer”) to discharge the functions and duties specified in this Agreement, and shall notify to the Concessionaire the name, address and the date of appointment of the Authority’s Engineer forthwith.
11.1.3 Within 30 (thirty) days of the Appointed Date, the Concessionaire shall submit to the Authority and the Authority’s Engineer a programme (the “Programme”) for Construction of Works, developed using networking techniques and giving the following details:
(a) the order in which the Concessionaire intends to carry out the Works, including the anticipated timing of design and stages of Works;
(b) the periods for reviews under Clause 11.2; and
(c) the sequence and timing of inspections and Tests specified in this Agreement. The Concessionaire shall submit a revised Programme whenever the previous Programme is inconsistent with the actual progress or with the Concessionaire’s obligations. Provided, however, that the Authority may, within a period of 15 (fifteen) days of receipt of the DPRProgramme, the Independent Engineer shall review the same and convey its observationscomments to the Concessionaire stating the modifications, if any to any, required for compliance with the Concessionaire.
12.1.4 In provisions of this Agreement, and the event that any modifications to the DPR Concessionaire shall have been determined under and in accordance with Clause 12.1.3carry out such modifications, the DPR shall be deemed to be modified to the extent thereofrequired for conforming with the provisions of this Agreement.