Operating and Maintenance Instructions. (a) Not less than six (6) months prior to the scheduled Substantial Completion Date, Developer shall deliver to PacifiCorp’s Representative one (1) set of preliminary operating and maintenance manuals sufficiently complete that the Facility, including the Equipment, may be safely commissioned and PacifiCorp’s personnel properly trained pursuant to Section 7.10. Developer shall, at its sole cost and expense, continuously update such manuals so that, as of three (3) months prior to the scheduled Substantial Completion Date, such operating and maintenance manuals are substantively in their final form with any amendments made as necessary. (b) Not less than three (3) months prior to the scheduled Substantial Completion Date, Developer shall supply to PacifiCorp three (3) copies of final operation and maintenance manuals, startup and shutdown manuals and the then current drawings of the Work as-built , in accordance with Appendix F and Appendix G. (c) All operating and maintenance manuals, startup and shutdown manuals and drawings of the Work as-built shall be in such detail as will enable PacifiCorp to operate, maintain, dismantle, reassemble, adjust and repair all parts of the Work, as described in Appendix F and Appendix G. Where this Agreement is terminated before the Substantial Completion Date (other than as a result of a PacifiCorp Default), Developer shall provide to PacifiCorp such information including copy drawings and Draft Manuals as is reasonable and as is necessary for PacifiCorp to complete, use and maintain the Work. (d) The provision by Developer of the final operation and maintenance manuals and drawings of the Work as-built in accordance with the provisions of this Section 15.5 shall be identified as a Milestone in Appendix B and the provisions of ARTICLE 10 shall apply.
Appears in 2 contracts
Operating and Maintenance Instructions. (a) Not less than six (6) months prior to the scheduled Guaranteed Substantial Completion Date, Developer Seller shall deliver to PacifiCorpBuyer’s Representative one (1) set of preliminary operating and maintenance manuals sufficiently complete that the Facility, including the Equipment, Plant and Equipment may be safely commissioned and PacifiCorpBuyer’s personnel properly trained pursuant to Section 7.107.11 (“Training”). Developer Seller shall, at its sole cost and expense, continuously update such manuals so that, as of three (3) months prior to the scheduled Substantial Completion Closing Date, such operating and maintenance manuals are substantively in their final form with any amendments made as necessary.
(b) Not less than Within three (3) months prior to of the scheduled Substantial Completion Closing Date, Developer Seller shall supply to PacifiCorp Buyer three (3) copies of final operation and maintenance manuals, startup and shutdown manuals and the then current drawings of the Work asas- built plus five (5) CD-built , in accordance with Appendix F and Appendix G.ROMs incorporating any changes made during testing and/or Commissioning of the Work.
(c) All operating and maintenance manuals, startup and shutdown manuals and drawings of the Work as-built shall be in such detail as will enable PacifiCorp Buyer to operate, maintain, dismantle, reassemble, adjust and repair all parts of the Work, as described in Appendix F and Appendix G. . Where this Agreement the employment of Seller is terminated before for default or in the Substantial Completion Date (other than as a result case of a PacifiCorp Default)Seller’s Material Adverse Change prior to the Transfer of Possession and Control of Project to Buyer Date, Developer Seller shall provide to PacifiCorp Buyer such information including copy drawings and Draft Manuals as is reasonable and as is necessary for PacifiCorp Buyer to complete, use and maintain the Work.
(d) The provision by Developer Seller of the final operation and maintenance manuals and drawings of the Work as-built in accordance with the provisions of this Section 15.5 shall be identified as a Milestone in Appendix B C and the provisions of ARTICLE article 10 (“Project Schedule”) shall apply.
Appears in 2 contracts
Operating and Maintenance Instructions.
(a) Not less than six (6) months prior to the scheduled Guaranteed Substantial Completion Date, Developer Seller shall deliver to PacifiCorpBuyer’s Representative one (1) set of preliminary operating and maintenance manuals sufficiently complete that the Facility, including the Equipment, Plant and Equipment may be safely commissioned and PacifiCorpBuyer’s personnel properly trained pursuant to Section 7.107.11 (“Training”). Developer Seller shall, at its sole cost and expense, continuously update such manuals so that, as of three (3) months prior to the scheduled Substantial Completion Closing Date, such operating and maintenance manuals are substantively in their final form with any amendments made as necessary.
(b) Not less than Within three (3) months prior to of the scheduled Substantial Completion Closing Date, Developer Seller shall supply to PacifiCorp Buyer three (3) copies of final operation and maintenance manuals, startup and shutdown manuals and the then current drawings of the Work asas- built plus five (5) CD-built , in accordance with Appendix F and Appendix G.ROMs incorporating any changes made during testing and/or Commissioning of the Work.
(c) All operating and maintenance manuals, startup and shutdown manuals and drawings of the Work as-built shall be in such detail as will enable PacifiCorp Buyer to operate, maintain, dismantle, reassemble, adjust and repair all parts of the Work, as described in Appendix F and Appendix G. . Where this Agreement the employment of Seller is terminated before for default or in the Substantial Completion Date (other than as a result case of a PacifiCorp Default)Seller’s Material Adverse Change prior to the Transfer of Possession and Control of Project to Buyer Date, Developer Seller shall provide to PacifiCorp Buyer such information including copy drawings and Draft Manuals as is reasonable and as is necessary for PacifiCorp Buyer to complete, use and maintain the Work.
(d) The provision by Developer Seller of the final operation and maintenance manuals and drawings of the Work as-built in accordance with the provisions of this Section 15.5 shall be identified as a Milestone in Appendix B C and the provisions of ARTICLE article 10 (“Project Schedule”) shall apply.
Appears in 2 contracts
Sources: Asset Purchase and Sale Agreement, Asset Purchase and Sale Agreement
Operating and Maintenance Instructions.
(a) Not less than six (6) months prior to the scheduled Guaranteed Substantial Completion Date, Developer Seller shall deliver to PacifiCorpBuyer’s Representative one (1) set of preliminary operating and maintenance manuals sufficiently complete that the Facility, including the Equipment, Plant and Equipment may be safely commissioned and PacifiCorpBuyer’s personnel properly trained pursuant to Section 7.107.11 (“Training”). Developer Seller shall, at its sole cost and expense, continuously update such manuals so that, as of three (3) months prior to the scheduled Substantial Completion Closing Date, such operating and maintenance manuals are substantively in their final form with any amendments made as necessary.
(b) Not less than Within three (3) months prior to of the scheduled Substantial Completion Closing Date, Developer Seller shall supply to PacifiCorp Buyer three (3) copies of final operation and maintenance manuals, startup and shutdown manuals and the then current drawings of the Work as-built , in accordance with Appendix F and Appendix G.plus five (5) CD-ROMs incorporating any changes made during testing and/or Commissioning of the Work.
(c) All operating and maintenance manuals, startup and shutdown manuals and drawings of the Work as-built shall be in such detail as will enable PacifiCorp Buyer to operate, maintain, dismantle, reassemble, adjust and repair all parts of the Work, as described in Appendix F and Appendix G. . Where this Agreement the employment of Seller is terminated before for default or in the Substantial Completion Date (other than as a result case of a PacifiCorp Default)Seller’s Material Adverse Change prior to the Transfer of Possession and Control of Project to Buyer Date, Developer Seller shall provide to PacifiCorp Buyer such information including copy drawings and Draft Manuals as is reasonable and as is necessary for PacifiCorp Buyer to complete, use and maintain the Work.
(d) The provision by Developer Seller of the final operation and maintenance manuals and drawings of the Work as-built in accordance with the provisions of this Section 15.5 shall be identified as a Milestone in Appendix B C and the provisions of ARTICLE article 10 (“Project Schedule”) shall apply.
Appears in 1 contract
Sources: Asset Purchase and Sale Agreement
Operating and Maintenance Instructions. (a) Not less than six (6) months prior to the scheduled Guaranteed Substantial Completion Date, Developer Contractor shall deliver to PacifiCorpCompany’s Representative one (1) set of preliminary operating and maintenance manuals sufficiently complete that the Facility, including the Equipment, Plant and Equipment may be safely commissioned and PacifiCorpCompany’s personnel properly trained pursuant to Section 7.107.11 (“Training”). Developer Contractor shall, at its sole cost and expense, continuously update such manuals so that, as of three (3) months prior to the scheduled Substantial Completion Date, such operating and maintenance manuals are substantively in their final form with any amendments made as necessary.
(b) Not less than Within three (3) months prior to of the scheduled Substantial Completion Date, Developer Contractor shall supply to PacifiCorp Company three (3) copies of final operation and maintenance manuals, startup and shutdown manuals and the then current drawings of the Work as-built , in accordance with Appendix F and Appendix G.plus five (5) CD-ROMs incorporating any changes made during testing and/or Commissioning of the Work.
(c) All operating and maintenance manuals, startup and shutdown manuals and drawings of the Work as-built shall be in such detail as will enable PacifiCorp Company to operate, maintain, dismantle, reassemble, adjust and repair all parts of the Work, as described in Appendix F and Appendix G. . Where this Agreement the employment of Contractor is terminated before for default or in the Substantial Completion Date (other than as a result case of a PacifiCorp Default)Contractor’s Material Adverse Change prior to the Transfer of Possession and Control of Project to Company Date, Developer Contractor shall provide to PacifiCorp Company such information including copy drawings and Draft Manuals as is reasonable and as is necessary for PacifiCorp Company to complete, use and maintain the Work.
(d) Where the employment of Contractor is terminated for convenience, Contractor shall provide to Company such information, including copy drawings and Draft Manuals, in the state of completion at the date of such termination.
(e) The provision by Developer Contractor of the final operation and maintenance manuals and drawings of the Work as-built in accordance with the provisions of this Section 15.5 shall be identified as a Milestone in Appendix B C and the provisions of ARTICLE 10 shall article 10shall apply.
Appears in 1 contract
Operating and Maintenance Instructions. (a) Not less than six (6) months prior to the scheduled Guaranteed Substantial Completion Date, Developer Seller shall deliver to PacifiCorpBuyer’s Representative one (1) set of preliminary operating and maintenance manuals sufficiently complete that the Facility, including the Equipment, Plant and Equipment may be safely commissioned and PacifiCorpBuyer’s personnel properly trained pursuant to Section 7.107.10 (“Training”). Developer Seller shall, at its sole cost and expense, continuously update such manuals so that, as of three (3) months prior to the scheduled Substantial Completion Closing Date, such operating and maintenance manuals are substantively in their final form with any amendments made as necessary.
(b) Not less than Within three (3) months prior to of the scheduled Substantial Completion Closing Date, Developer Seller shall supply to PacifiCorp Buyer three (3) copies of final operation and maintenance manuals, startup and shutdown manuals and the then current drawings of the Work as-built , in accordance with Appendix F and Appendix G.plus five (5) CD-ROMs incorporating any changes made during testing and/or Commissioning of the Work.
(c) All operating and maintenance manuals, startup and shutdown manuals and drawings of the Work as-built shall be in such detail as will enable PacifiCorp Buyer to operate, maintain, dismantle, reassemble, adjust and repair all parts of the Work, as described in Appendix F and Appendix G. . Where this Agreement the employment of Seller is terminated before for default or in the Substantial Completion Date (other than as a result case of a PacifiCorp Default)Seller’s Material Adverse Change prior to the Transfer of Possession and Control of Project to Buyer Date, Developer Seller shall provide to PacifiCorp Buyer such information including copy drawings and Draft Manuals as is reasonable and as is necessary for PacifiCorp Buyer to complete, use and maintain the Work.
(d) The provision by Developer Seller of the final operation and maintenance manuals and drawings of the Work as-built in accordance with the provisions of this Section 15.5 shall be identified as a Milestone in Appendix B C and the provisions of ARTICLE article 10 (“Project Schedule”) shall apply.