Common use of Operational Readiness Certificate Clause in Contracts

Operational Readiness Certificate. When WMATA has confirmed that Operational Readiness has occurred, WMATA, Owner and Contractor shall jointly execute an Operational Readiness Certificate setting forth the Operational Readiness Date. Neither WMATA’s concurrence that the Operational Readiness Date has occurred nor execution of the Operational Readiness Certificate shall relieve Contractor of any of its obligations under the Contract Documents.

Appears in 2 contracts

Sources: Design Build Contract, Design Build Contract