Other Delays. It is hereby clarified that ISR shall not bear any responsibility and/or liability in connection with any and all delays that may occur in the Project (including, but without derogating from the generality of the above, pursuant to Force Majeure events), all except Entitling Delays and Suspension, which in relation thereto the provisions of Sections 9.5 or 9.6 above (as applicable) shall apply, all unless expressly provided to the contrary in these General Terms. Without derogating from the above, the Contractor shall not be entitled to any payment and/or any remedy or relief, of whatever kind and nature, from ISR in connection with any and all delays and suspensions in the Project, unless entitled to it pursuant to an express provision in these General Terms.
Appears in 3 contracts
Sources: General Terms Agreement, Design–build Agreement, General Terms