Common use of OTHER PERMITS AND APPROVALS Clause in Contracts

OTHER PERMITS AND APPROVALS. APPROVAL TO CONSTRUCT PIPELINES AND CABLES FROM MAIN MILL SITE TO THE SITE AT THE ELBE RIVER. Owner has made agreements with the owner(s) of the land where the pipelines and electrical and signal cables will be located between the main site arid the Elbe River site. Owner shall secure approval for Contractor's use of this road and for construction by Contractor of the piping and electrical works between the two sites, and the construction of approximately 50 meters of access road between these two sites. Owner shall apply for certain permits related to water drainage.

Appears in 2 contracts

Sources: Engineering, Design, Procurement, Construction Agreement (Mercer International Inc), Contract for Engineering, Design, Procurement, Construction, Erection and Start Up of a Kraft Pulp Mill (Mercer International Inc)