Common use of OUT OF THE WORKS Clause in Contracts

OUT OF THE WORKS. 8.1 The Contractor shall establish the boundary pegs or beacons identifying the site and the correctness of the datum level. 8.2 The Contractor shall define the levels which are required for the execution of the Works. 8.3 The Contractor shall take all necessary precautions to preserve such pegs, beacons, datum levels and other aids used in setting out the Works. 8.4 The Contractor reserves the right to alter the position of any drain or drain pipe as shown on the Building Plan to suit the level of the ground, should it be necessary.

Appears in 3 contracts

Sources: Building Agreement, Building Agreement, Building Agreement