Common use of OVER PAYMENTS / UNDER PAYMENTS DETECTED DURING TECHNICAL AUDIT Clause in Contracts

OVER PAYMENTS / UNDER PAYMENTS DETECTED DURING TECHNICAL AUDIT. The Company reserves the right to carry out post-payment audit and technical examination of the running/ final bill including all supporting vouchers etc. The Company also reserves the right to propose recoveries detected by CVC (Central Vigilance Commission) based on their audit and observations of works / bills etc. The Company further reserves the right to enforce recovery of any over payment when detected, notwithstanding the fact the amount of running / final bill may be included by one of the parties as an item of dispute before an arbitrator appointed and notwithstanding the fact that the amount of running / final bill figures in the arbitration award.

Appears in 2 contracts

Sources: Annual Maintenance Contract, Construction Contract