Oversight and Acceptance. Design-Builder shall not be relieved of its obligation to perform the Work in accordance with the Contract Documents, or any of its other obligations under the Contract Documents, by oversight, spot checks, audits, reviews, tests, inspections, Hold Points, Acceptances or Approvals by any Persons, or by any failure of any Person to take this action. The oversight, spot checks, audits, reviews, tests, inspections, Hold Points, Acceptances, and Approvals by any Person do not constitute Final Acceptance of the Material or Work, or a waiver of any legal or equitable right regarding the Material or Work. VPRA may reject or require Design-Builder to remedy any Nonconforming Work and/or VPRA may identify additional Work that must be performed to bring the Project into compliance with the requirements of the Contract Documents at any time before Final Acceptance, whether or not previous oversight, spot checks, audits, reviews, tests, inspections, Hold Points, Acceptances or Approvals were conducted or provided by any Person.
Appears in 2 contracts
Sources: Design Build Agreement, Design Build Agreement
Oversight and Acceptance. Design-Builder Contractor shall not be relieved of its obligation to perform the Work in accordance with the Contract Documents, or any of its other obligations under the Contract Documents, by oversight, spot checks, audits, reviews, tests, inspections, Hold Points, Acceptances or Approvals by any Persons, or by any failure of any Person to take this action. The oversight, spot checks, audits, reviews, tests, inspections, Hold Points, Acceptances, and Approvals by any Person do not constitute Final Acceptance of the Material or Work, or a waiver of any legal or equitable right regarding the Material or Work. VPRA may reject or require Design-Builder Contractor to remedy any Nonconforming Work and/or VPRA may identify additional Work that must be performed done to bring the Project into compliance with the requirements of the Contract Documents at any time before Final Acceptance, whether or not previous oversight, spot checks, audits, reviews, tests, inspections, Hold Points, Acceptances or Approvals were conducted or provided by any Person.
Appears in 1 contract
Sources: Construction Manager / General Contractor Agreement