OVERSIZE. (1) If the City requires a sanitary sewer either within or external to the Development Area to be larger than necessary to serve the Development Area: (a) all such Oversize sanitary sewer lines shall be designated at the time the Construction Drawings are given final approval by the Manager, Urban Development; (b) the City shall pay, from the Developer Funded Infrastructure Stabilization Fund - Utility Oversize to the Developer of Record the additional cost of such larger size pipe and accessories as approved by and in the sole discretion of the Manager, Urban Development, at prices in accordance with the Unit Rate Schedule; and (c) the City shall not make any payments from the Developer Funded Infrastructure Stabilization Fund - Utility Oversize unless: (i) the line is established as Oversize in the Construction Drawings approved by the Manager, Urban Development prior to the signing of the Special Clauses Agreement; and (ii) the internal diameter of the sanitary sewer pipe exceeds three hundred millimetres (300 mm). (a) In areas where the sanitary sewer mains are located deeper than six (6) metres, a dual sewer system may be required and the Developer of Record will be entitled to an Oversize recovery for all mains installed at a depth of six (6) metres or more to crown of pipe; (b) The dual sewer system requirement shall be determined as early as possible in the approval process; and (c) The City shall pay, from the Developer Funded Infrastructure Stabilization Fund - Utility Oversize to the Developer of Record the additional cost of the oversized portion of the mains that are located deeper than six (6) metres underground as approved by the Manager, Urban Development, at prices in accordance with the Unit Rate Schedule.
Appears in 6 contracts
Sources: Master Industrial Development Agreement, Master Residential Development Agreement, Master Commercial Development Agreement
OVERSIZE. (1) If the City requires a sanitary storm sewer either within or external to the Development Area to be larger than necessary to serve the Development Area:
(a) all such Oversize sanitary storm sewer lines shall be designated at the time the Construction Drawings are given final approval by the Manager, Urban DevelopmentSenior Infrastructure Engineer;
(b) the City shall pay, pay from the Developer Funded Infrastructure Stabilization Fund - Utility Oversize to the Developer of Record the additional cost of such larger size pipe and accessories as approved by and in the sole discretion of the ManagerManaging Director, Urban DevelopmentCalgary Approvals Coordination, at prices in accordance with the Unit Rate Schedule; and
(c) the City shall not make any payments from the Developer Funded Infrastructure Stabilization Fund - Utility Oversize unless:
(i) unless the line is established as Oversize in the Construction Drawings approved by the Manager, Urban Development Senior Infrastructure Engineer prior to the signing of the Special Clauses Agreement; and
(ii) the internal diameter of the sanitary sewer pipe exceeds three hundred millimetres (300 mm).
(a) In areas where the sanitary storm sewer mains are located deeper than six (6) metres, a dual sewer system may be required and the Developer of Record will be entitled to an Oversize recovery for all mains installed at a depth of six (6) metres meters or more to crown of pipe;
(b) The the dual sewer system requirement shall be determined as early as possible in the approval process; and
(c) The City shall pay, from the Developer Funded Infrastructure Stabilization Fund - Utility Oversize Oversize, to the Developer of Record Record, the additional cost of the oversized portion of the mains that are located deeper than six (6) metres underground as approved by the ManagerManaging Director, Urban DevelopmentCalgary Approvals Coordination, at prices in accordance with the Unit Rate Schedule.
Appears in 3 contracts
Sources: Master Development Agreement, Master Development Agreement, Master Development Agreement
OVERSIZE. (1) If the City requires a sanitary sewer either within or external to the Development Area to be larger than necessary to serve the Development Area:
(a) all such Oversize sanitary sewer lines shall be designated at the time on the Construction Drawings are given final approval and approved by the Manager, Urban DevelopmentDevelopment Engineer;
(b) the City shall pay, from the Developer Funded Infrastructure Stabilization Fund - Utility Oversize to the Developer of Record the additional cost of such larger size pipe and accessories as approved by and in the sole discretion of the Manager, Urban DevelopmentDevelopment Engineering, at prices in accordance with the Unit Rate Schedule; and
(c) the City shall not make any payments from the Developer Funded Infrastructure Stabilization Fund - Utility Oversize unless:
(i) the line is established and approved as Oversize in at the time the Construction Drawings approved are given final approval by the Manager, Urban Development prior to the signing of the Special Clauses AgreementEngineer; and
(ii) the internal diameter of the sanitary sewer pipe exceeds three hundred millimetres (300 mm).
(a) In areas where the sanitary sewer mains are located deeper than six (6) metres, a dual sewer system may be required and the Developer of Record will be entitled to an Oversize recovery for all mains installed at a depth of six (6) metres or more to crown of pipe;
(b) The dual sewer system requirement shall be determined as early as possible in the approval process; and
(c) The City shall pay, pay from the Developer Funded Infrastructure Stabilization Fund - Utility Oversize to the Developer of Record the additional cost of the oversized portion of the mains that are located deeper than six (6) metres underground as approved by the Manager, Urban DevelopmentDevelopment Engineering, at prices in accordance with the Unit Rate Schedule.
Appears in 2 contracts
Sources: Development Agreement, Development Agreement
OVERSIZE. (1) If the City requires a sanitary storm sewer either within or external to the Development Area to be larger than necessary to serve the Development Area:
(a) all such Oversize sanitary storm sewer lines shall be designated at the time the Construction Drawings are given final approval by the Manager, Urban DevelopmentDevelopment Engineer;
(b) the City shall pay, pay from the Developer Funded Infrastructure Stabilization Fund - Utility Oversize to the Developer of Record the additional cost of such larger size pipe and accessories as approved by and in the sole discretion of the ManagerManaging Director, Urban DevelopmentCalgary Approvals Coordination, at prices in accordance with the Unit Rate Schedule; and
(c) the City shall not make any payments from the Developer Funded Infrastructure Stabilization Fund - Utility Oversize unless:
(i) unless the line is established as Oversize in the Construction Drawings approved by the Manager, Urban Development Engineer prior to the signing of the Special Clauses Interim Indemnity Agreement; and
(ii) the internal diameter of the sanitary sewer pipe exceeds three hundred millimetres (300 mm).
(a) In areas where the sanitary storm sewer mains are located deeper than six (6) metres, a dual sewer system may be required and the Developer of Record will be entitled to an Oversize recovery for all mains installed at a depth of six (6) metres meters or more to crown of pipe;
(b) The the dual sewer system requirement shall be determined as early as possible in the approval process; and
(c) The City shall pay, from the Developer Funded Infrastructure Stabilization Fund - Utility Oversize Oversize, to the Developer of Record Record, the additional cost of the oversized portion of the mains that are located deeper than six (6) metres underground as approved by the ManagerManaging Director, Urban DevelopmentCalgary Approvals Coordination, at prices in accordance with the Unit Rate Schedule.
Appears in 1 contract
Sources: Master Development Agreement