Owner Access. (a) Subject to Section 17.1(b) but without limiting any of Owner’s rights in respect of the Site, Project Co acknowledges and agrees that Owner, the Owner Parties and ▇▇▇▇▇▇’s Consultant shall have unrestricted access to the Site, the Facility and any workshop where materials, plant or equipment are being manufactured, prepared or stored, at all reasonable times, during normal working hours. Project Co shall provide sufficient, safe and proper facilities at all times for the review of the Work by the Consultant and the inspection of the Work by authorized agencies. If parts of the Work are in preparation at locations other then the Site, Owner and the Consultant, Owner’s Project Manager and ▇▇▇▇▇▇’s Consultant shall be given access to such Work wherever it is in progress upon reasonable notice and during normal business hours. (b) In exercising their access rights under Section 17.1(a), Owner and the Owner Parties shall comply with all relevant safety procedures and any reasonable directions with regard to site safety that may be issued by or on behalf of Project Co from time to time. (c) If Work is designated for tests, inspections, or approvals in the Contract Documents, or by the Consultant’s instructions, or pursuant to Applicable Law, Project Co shall give the Consultant reasonable notice of when the Work will be ready for review and inspection. Project Co shall arrange for and shall give the Consultant reasonable notice of the date and time of inspections by other authorities. (d) Project Co shall furnish promptly to the Consultant 2 copies of certificates and inspection reports relating to the Work.
Appears in 3 contracts
Sources: Project Agreement, Project Agreement, Project Agreement
Owner Access. (a) Subject to Section 17.1(b) but without limiting any of Owner’s rights in respect of the Site, Project Co acknowledges and agrees that Owner, the Owner Parties and ▇▇▇▇▇▇Lender’s Consultant shall have unrestricted access to the Site, the Facility and any workshop where materials, plant or equipment are being manufactured, prepared or stored, at all reasonable times, during normal working hours. Project Co shall provide sufficient, safe and proper facilities at all times for the review of the Work by the Consultant and the inspection of the Work by authorized agencies. If parts of the Work are in preparation at locations other then the Site, Owner and the Consultant, Owner’s Project Manager and ▇▇▇▇▇▇Lender’s Consultant shall be given access to such Work wherever it is in progress upon reasonable notice and during normal business hours.
(b) In exercising their access rights under Section 17.1(a), Owner and the Owner Parties shall comply with all relevant safety procedures and any reasonable directions with regard to site safety that may be issued by or on behalf of Project Co from time to time.
(c) If Work is designated for tests, inspections, or approvals in the Contract Documents, or by the Consultant’s instructions, or pursuant to Applicable Law, Project Co shall give the Consultant reasonable notice of when the Work will be ready for review and inspection. Project Co shall arrange for and shall give the Consultant reasonable notice of the date and time of inspections by other authorities.
(d) Project Co shall furnish promptly to the Consultant 2 copies of certificates and inspection reports relating to the Work.
Appears in 2 contracts
Sources: Project Agreement, Project Agreement
Owner Access. (a) Subject to Section 17.1(b) but without limiting any of Owner’s rights in respect of the Site, Project Co acknowledges and agrees that Owner, the Owner Parties and ▇▇▇▇▇▇Lender’s Consultant shall have unrestricted access to the Site, the Facility and any workshop where materials, plant or equipment are being manufactured, prepared or stored, at all reasonable times, during normal working hours. Project Co shall provide sufficient, safe and proper facilities at all times for the review of the Work by the Consultant and the inspection of the Work by authorized agencies. If parts of the Work are in preparation at locations other then than the Site, Owner and the Consultant, Owner’s Project Manager and ▇▇▇▇▇▇Lender’s Consultant shall be given access to such Work wherever it is in progress upon reasonable notice and during normal business hours.
(b) In exercising their access rights under Section 17.1(a), Owner and the Owner Parties shall comply with all relevant safety procedures and any reasonable directions with regard to site safety that may be issued by or on behalf of Project Co from time to time.
(c) If Work is designated for tests, inspections, or approvals in the Contract Documents, or by the Consultant’s instructions, or pursuant to Applicable Law, Project Co shall give the Consultant reasonable notice of when the Work will be ready for review and inspection. Project Co shall arrange for and shall give the Consultant reasonable notice of the date and time of inspections by other authorities.
(d) Project Co shall furnish promptly to the Consultant 2 copies of certificates and inspection reports relating to the Work.
Appears in 1 contract
Sources: Project Agreement
Owner Access. (a) Subject to Section 17.1(b) but without limiting any of Owner’s Owner‟s rights in respect of the Site, Project Co acknowledges and agrees that Owner, the Owner Parties and ▇▇▇▇▇▇’s ‟s Consultant shall have unrestricted access to the Site, the Facility and any workshop where materials, plant or equipment are being manufactured, prepared or stored, at all reasonable times, during normal working hours. Project Co shall provide sufficient, safe and proper facilities at all times for the review of the Work by the Consultant and the inspection of the Work by authorized agencies. If parts of the Work are in preparation at locations other then than the Site, Owner and the Consultant, Owner’s the Owner‟s Project Manager and ▇▇▇▇▇▇’s ‟s Consultant shall be given access to such Work wherever it is in progress upon reasonable notice and during normal business hours.
(b) In exercising their access rights under Section 17.1(a), Owner and the Owner Parties shall comply with all relevant safety procedures and any reasonable directions with regard to site safety that may be issued by or on behalf of Project Co from time to time.
(c) If Work is designated for tests, inspections, or approvals in the Contract Documents, or by the Consultant’s Consultant‟s instructions, or pursuant to Applicable Law, Project Co shall give the Consultant reasonable notice of when the Work will be ready for review and inspection. Project Co shall arrange for and shall give the Consultant reasonable notice of the date and time of inspections by other authorities.
(d) Project Co shall furnish promptly to the Consultant 2 copies of certificates and inspection reports relating to the Work.
Appears in 1 contract
Sources: Project Agreement
Owner Access. (a) Subject to Section 17.1(b) but without limiting any of Owner’s rights in respect of the Site, Project Co acknowledges and agrees that Owner, the Owner Parties and ▇▇▇▇▇▇Senior Lender’s Consultant shall have unrestricted access to the Site, the Facility and any workshop where materials, plant or equipment are being manufactured, prepared or stored, at all reasonable times, during normal working hours. Project Co shall provide sufficient, safe and proper facilities at all times for the review of the Work by the Consultant and the inspection of the Work by authorized agencies. If parts of the Work are in preparation at locations other then the Site, Owner and the Consultant, Owner’s Project Manager and ▇▇▇▇▇▇Senior Lender’s Consultant shall be given access to such Work wherever it is in progress upon reasonable notice and during normal business hours.
(b) In exercising their access rights under Section 17.1(a), Owner and the Owner Parties shall comply with all relevant safety procedures and any reasonable directions with regard to site safety that may be issued by or on behalf of Project Co from time to time.
(c) If Work is designated for tests, inspections, or approvals in the Contract Documents, or by the Consultant’s instructions, or pursuant to Applicable Law, Project Co shall give the Consultant reasonable notice of when the Work will be ready for review and inspection. Project Co shall arrange for and shall give the Consultant reasonable notice of the date and time of inspections by other authorities.
(d) Project Co shall furnish promptly to the Consultant 2 copies of certificates and inspection reports relating to the Work.
Appears in 1 contract
Sources: Project Agreement