Owner Direct Purchase Program. 4.2.7.1 Owner has elected to participate in a direct purchase program whereby it purchases materials and equipment costing $5,000 and over directly from the supplier of such materials or equipment in order to achieve sales tax savings. Such materials and equipment purchased through this program are referred to as “ODP.” Owner shall prepare purchase orders to the supplier(s) of the ODP. Contractor shall allow three (3) weeks for execution of all such purchase orders by Owner. Contractor shall provide Owner an ODP matrix (including CSI division, description of materials, cost, lead time of material, potential tax savings, date ODP request will be submitted to Owner, date which purchase order must be issued in order not to cause delay). Any delay caused by improper paperwork/documentation by the Contractor, or its subcontractors, vendors or suppliers, shall be the responsibility of Contractor. Contractor use its best efforts to maximize cost savings for the project and to cooperate with Owner in utilizing its sales tax savings program. Within thirty (30) days after the project specific PO is issued, Contractor will process one (1) or more deductive Change Orders under the Contract for the entire estimated amount of ODP, inclusive of sales taxes. Prior to final payment, a reconciliation will be performed and, if necessary, a Potential Change Order (hereinafter defined) will be prepared for Owner’s review and approval. 4.2.8.2 With respect to all ODP, Contractor shall remain responsible for coordinating, ordering, inspecting, accepting delivery, storing, handling, installing, warranting and quality control for all ODP, and such obligations shall remain subject to the Bonds (hereinafter defined). Notwithstanding anything herein to the contrary, Contractor expressly acknowledges and agrees that any materials or equipment directly purchased by Owner pursuant this Section 4.2.8 shall be included within and covered to the same extent as all other warranties provided by Contractor pursuant to the terms of the Contract Documents. Contractor shall be responsible for safeguarding all ODP on the project site on Owner’s behalf.
Appears in 1 contract
Owner Direct Purchase Program. 4.2.7.1 3.6.6.1 Owner has elected to participate in a direct purchase program whereby it purchases materials and equipment costing $5,000 and over directly from the supplier of such materials or equipment in order to achieve sales tax savings. Such materials and equipment purchased through this program are referred to as “ODP.” Owner shall prepare purchase orders to the supplier(s) of the ODP. Contractor Construction Manager shall allow three (3) weeks for execution of all such purchase orders by Owner. Contractor Construction Manager shall provide Owner an a ODP matrix (including CSI division, description of materials, cost, lead time of material, potential tax savings, date ODP request will be submitted to Owner, date which purchase order must be issued in order not to cause delay)) together with the GMP. Any delay caused by improper paperwork/documentation by the ContractorConstruction Manager, or its subcontractors, vendors or suppliers, shall be the responsibility of ContractorConstruction Manager. Contractor Construction Manager use its best efforts to maximize cost savings for the project Project and to cooperate with Owner in utilizing its sales tax savings program. Within thirty (30) days after the project specific PO GMP is issuedestablished, Contractor Construction Manager will process one (1) or more deductive Change Orders under the Contract for the entire estimated amount of ODP, inclusive of sales taxes. Prior to final payment, a reconciliation will be performed and, if necessary, a Potential Change Order (hereinafter defined) will be prepared for Owner’s review and approval.
4.2.8.2 3.6.6.2 With respect to all ODP, Contractor Construction Manager shall remain responsible for coordinating, ordering, inspecting, accepting delivery, storing, handling, installing, warranting and quality control for all ODP, and such obligations shall remain subject to the Bonds (hereinafter defined). Notwithstanding anything herein to the contrary, Contractor Construction Manager expressly acknowledges and agrees that any materials or equipment directly purchased by Owner pursuant this Section 4.2.8 3.6.6 shall be included within and covered to the same extent as all other warranties provided by Contractor Construction Manager pursuant to the terms of the Contract Documents. Contractor Construction Manager shall be responsible for safeguarding all ODP on the project site Project Site on Owner’s behalf.
Appears in 1 contract
Sources: Construction Management Agreement
Owner Direct Purchase Program. 4.2.7.1 4.2.8.1 Owner has elected to participate in a direct purchase program whereby it purchases materials and equipment costing $5,000 and over directly from the supplier of such materials or equipment in order to achieve sales tax savings. Such materials and equipment purchased through this program are referred to as “ODP.” Owner shall prepare purchase orders to the supplier(s) of the ODP. Contractor shall allow three (3) weeks for execution of all such purchase orders by Owner. Contractor shall provide Owner an ODP matrix (including CSI division, description of materials, cost, lead time of material, potential tax savings, date ODP request will be submitted to Owner, date which purchase order must be issued in order not to cause delay). Any delay caused by improper paperwork/documentation by the Contractor, or its subcontractors, vendors or suppliers, shall be the responsibility of Contractor. Contractor use its best efforts to maximize cost savings for the project and to cooperate with Owner in utilizing its sales tax savings program. Within thirty (30) days after the project specific PO is issued, Contractor will process one (1) or more deductive Change Orders under the Contract for the entire estimated amount of ODP, inclusive of sales taxes. Prior to the final payment, a reconciliation will be performed and, if necessary, a Potential Change Order (hereinafter defined) will be prepared for Owner’s review and approval.
4.2.8.2 With respect to all ODP, Contractor shall remain responsible for coordinating, ordering, inspecting, accepting delivery, storing, handling, installing, warranting and quality control for all ODP, and such obligations shall remain subject to the Bonds (hereinafter defined). Notwithstanding anything herein to the contrary, Contractor expressly acknowledges and agrees that any materials or equipment directly purchased by Owner pursuant this Section 4.2.8 4.2.8.2 shall be included within and covered to the same extent as all other warranties provided by Contractor pursuant to the terms of the Contract Documents. Contractor shall be responsible for safeguarding all ODP on the project site on Owner’s behalf.
Appears in 1 contract
Owner Direct Purchase Program. 4.2.7.1 3.6.6.1 Owner has elected to participate in a direct purchase program whereby it purchases materials and equipment costing $5,000 and over directly from the supplier of such materials or equipment in order to achieve sales tax savings. Such materials and equipment purchased through this program are referred to as “ODP.” Owner shall prepare purchase orders to the supplier(s) of the ODPDOP. Contractor Construction Manager shall allow three (3) weeks for execution of all such purchase orders by Owner. Contractor Construction Manager shall provide Owner an a ODP matrix (including CSI division, description of materials, cost, lead time of material, potential tax savings, date ODP request will be submitted to Owner, date which purchase order must be issued in order not to cause delay)) together with the GMP. Any delay caused by improper paperwork/documentation by the ContractorConstruction Manager, or its subcontractors, vendors or suppliers, shall be the responsibility of ContractorConstruction Manager. Contractor Construction Manager use its best efforts to maximize cost savings for the project Project and to cooperate with Owner in utilizing its sales tax savings program. Within thirty (30) days after the project specific PO GMP is issuedestablished, Contractor Construction Manager will process one (1) or more deductive Change Orders under the Contract for the entire estimated amount of ODP, inclusive of sales taxes. Prior to the final payment, a reconciliation will be performed and and, if necessary, a Potential Change Order (hereinafter defined) will be prepared for Owner’s review and approval.
4.2.8.2 3.6.6.2 With respect to all ODP, Contractor Construction Manager shall remain responsible for coordinating, ordering, inspecting, accepting delivery, storing, handling, installing, warranting and quality control for all ODP, and such obligations shall remain subject to the Bonds (hereinafter defined). Notwithstanding anything herein to the contrary, Contractor Construction Manager expressly acknowledges and agrees that any materials or equipment directly purchased by Owner pursuant this Section 4.2.8 Subsection 3.6.6 shall be included within and covered to the same extent as all other warranties provided by Contractor Construction Manager pursuant to the terms of the Contract Documents. Contractor Construction Manager shall be responsible for safeguarding all ODP on the project site Project Site on Owner’s behalf.
Appears in 1 contract
Sources: Construction Management Agreement