Common use of Owner Right to Correct or Complete Defective Work Clause in Contracts

Owner Right to Correct or Complete Defective Work. 1. After Substantial Completion, and during the Defect Correction Period, and subject to Section 12.3B.2, if Contractor fails to commence the Corrective Work (which commencement may include the detailed planning associated with the on-Site implementation of the Corrective Work) within a reasonable period of time not to exceed [***] ([***]) Business Days after Contractor’s receipt of written notice from Owner or does not diligently perform such Corrective Work on an expedited basis (provided that Contractor’s timeline for performance shall be extended to the extent that Contractor is not provided reasonable access to those portions of the Train 4 Facility or the Phase 1 Facilities that have achieved Substantial Completion so that Contractor may commence, continue and complete the Corrective Work), then Owner, upon written notice to Contractor, may, as its sole and exclusive remedy for the Defect (except for its right to enforce Contractor’s indemnification obligations under this Agreement) perform such Corrective Work, and Contractor shall be liable to Owner for all reasonable costs and expenses incurred by Owner in connection with such Corrective Work and shall pay Owner (directly, by offset or by collection on the Letter of Credit, at Owner’s sole discretion) an amount equal to such costs and expenses; or 2. If any Defective Work (i) materially affects Train’s 1, Train 2’s, Train 3’s or Train 4’s production or loading capabilities and would put the Train 4 Facility at risk of being unable to operate or (ii) presents an imminent threat to the safety or health of any Person and Owner knows of such Defective Work, Owner may (in addition to any other remedies that it has under this Agreement) perform the Corrective Work without giving prior notice to Contractor (provided that Owner shall give Contractor notice of such event as soon as reasonably possible after becoming aware of such Defective Work), and, in such event, Contractor shall be liable to Owner for all reasonable costs and expenses incurred by Owner in connection with such Corrective Work and shall pay Owner (directly, by offset or by collection on the Letter of Credit, at Owner’s sole discretion) an amount equal to such costs and expenses (which costs and expenses shall be adequately documented and supported by Owner). If Corrective Work is performed by Owner on Defective Work without providing any advance notice to Contractor, then Contractor’s obligations to perform Corrective Work on such Defective Work shall no longer apply to such Defective Work (it being understood that, at Contractor’s cost, and in Owner’s sole discretion, Owner may be able to obtain a replacement warranty from a third-party with respect to such item of Defective Work), provided that Contractor’s obligations under this Agreement with respect to all other portions of the Train 4 Facility (including an portion of Equipment) shall continue in full force and effect, including continuing in full force and effect with respect to any portions of the item of the same Equipment or portion of the Train 4 Facility in which Owner performed the Corrective Work (except for the specific Defect being addressed).

Appears in 1 contract

Sources: Fixed Price Turnkey Agreement (NextDecade Corp.)

Owner Right to Correct or Complete Defective Work. 1. After Substantial CompletionCompletion of the applicable Train, and during the Defect Correction Period, and subject to Section 12.3B.2, if Contractor fails to commence the Corrective Work (which commencement may include the detailed planning associated with the on-Site implementation of the Corrective Work) within a reasonable period of time not to exceed [***] ([***]) Business Days after Contractor’s receipt of written notice from Owner or does not diligently perform such Corrective Work on an expedited basis (provided that Contractor’s timeline for performance shall be extended to the extent that Contractor is not provided reasonable access to those portions of the Train 4 Facility or the Phase 1 Facilities Train 3 Liquefaction Facility that have achieved Substantial Completion so that Contractor may commence, continue and complete the Corrective Work), then Owner, upon written notice to Contractor, may, may (as its sole and exclusive remedy for the Defect (except for its right to enforce Contractor’s indemnification obligations under this the Agreement) perform such Corrective Work, and Contractor shall be liable to Owner for all reasonable costs and expenses incurred by Owner in connection with such Corrective Work and shall pay Owner (directly, by offset or by collection on the Letter of Credit, at Owner’s sole discretion) an amount equal to such costs and expenses; or 2. If any Defective Work (i) materially affects Train’s Train 1’s, Train 2’s, Train 3’s or Train 43’s production or loading capabilities and would put the Train 4 Facility at risk of being unable to operate or (ii) presents an imminent threat to the safety or health of any Person and Owner knows of such Defective Work, Owner may (in addition to any other remedies that it has under this Agreement) perform the Corrective Work without giving prior notice to Contractor (provided that Owner shall give Contractor notice of such event as soon as reasonably possible after becoming aware of such Defective Work), and, in such event, Contractor shall be liable to Owner for all reasonable costs and expenses incurred by Owner in connection with such Corrective Work and shall pay Owner (directly, by offset or by collection on the Letter of Credit, at Owner’s sole discretion) an amount equal to such costs and expenses (which costs and expenses shall be adequately documented and supported by Owner). If Corrective Work is performed by Owner on Defective Work without providing any advance notice to Contractor, then Contractor’s obligations to perform Corrective Work on such Defective Work shall no longer apply to such Defective Work (it being understood that, at Contractor’s cost, and in Owner’s sole discretion, Owner may be able to obtain a replacement warranty from a third-party with respect to such item of Defective Work), provided that Contractor’s obligations under this Agreement with respect to all other portions of the Train 4 Facility (including an portion of Equipment) shall continue in full force and effect, including continuing in full force and effect with respect to any portions of the item of the same Equipment or portion of the Train 4 Facility in which Owner performed the Corrective Work (except for the specific Defect being addressed).

Appears in 1 contract

Sources: Fixed Price Turnkey Agreement (NextDecade Corp.)

Owner Right to Correct or Complete Defective Work. 1. After Substantial Completion, and during the Defect Correction Period, and subject to Section 12.3B.2, if If Contractor fails to commence the Corrective Work (which commencement may include the detailed planning associated with the on-Site implementation of the Corrective Work) within a reasonable period of time not to exceed [***] five ([***]5) Business Days after Contractor’s receipt of written notice from Owner Days, or does not diligently perform complete such Corrective Work on an expedited basis (provided that Contractor’s timeline for performance shall be extended to the extent that Contractor is not provided reasonable access to those portions of the Train 4 Facility or the Phase 1 Facilities that have achieved Substantial Completion so that Contractor may commence, continue and complete the Corrective Work)basis, then Owner, upon by written notice to Contractor, may, as its sole and exclusive remedy for the Defect may (except for its right in addition to enforce Contractor’s indemnification obligations any other remedies that it has under this Agreement, at law or in equity) perform such the Corrective Work, and Contractor shall be liable to Owner for all reasonable costs and expenses in excess of the GMP incurred by Owner in connection with such Corrective Work and arising out of or relating to such Defective Work and, if such costs exceed the GMP shall pay Owner (directly, by offset offset, or by collection on the Letter of Credit, at Owner’s sole discretion) ), an amount equal to such costs and expenses; or 2. If any provided, however, if such Defective Work (i) materially affects Train’s 1, Train 2’s, Train 3’s the operation or Train 4’s production use of any of the Project or loading capabilities and would put the Train 4 Facility at risk of being unable to operate or (ii) presents an imminent threat to the safety or health of any Person and Owner knows of such Defective Work, Owner may (in addition to any other remedies that it has under this Agreement, at law or in equity) perform the such Corrective Work without giving prior written notice to Contractor (provided that Owner shall give advise Contractor notice of such event action as soon as reasonably possible after becoming aware of such Defective Workpossible), and, in that event, such eventwork shall be charged against the GMP until the GMP is reached, and thereafter such costs shall be at the expense of Contractor. If Owner incurs any costs for such work in excess of the GMP, Contractor shall be liable to Owner for all reasonable costs and expenses incurred by Owner in connection with such Corrective Work and shall immediately pay Owner (directly, by offset offset, or by collection on the Letter of Credit, at Owner’s sole discretion) an amount equal to such ), all reasonable costs and expenses (which incurred by Owner in excess of the GMP in performing such Work. Upon Contractor’s request, Owner shall provide documentation identifying the costs and expenses shall be adequately documented and supported by Owner). If Corrective Work is performed by Owner on Defective Work without providing any advance notice to Contractor, then Contractor’s obligations to perform Corrective Work on complete such Defective Work shall no longer apply to such Defective Work (it being understood that, at Contractor’s cost, and in Owner’s sole discretion, Owner may be able to obtain a replacement warranty from a third-party with respect to such item of Defective Work), provided that Contractor’s obligations under this Agreement with respect to all other portions of the Train 4 Facility (including an portion of Equipment) shall continue in full force and effect, including continuing in full force and effect with respect to any portions of the item of the same Equipment or portion of the Train 4 Facility in which Owner performed the Corrective Work (except for the specific Defect being addressed).

Appears in 1 contract

Sources: Turnkey Agreement (Global Clean Energy Holdings, Inc.)

Owner Right to Correct or Complete Defective Work. 1. After Substantial Completion, and during the Defect Correction Period, and subject to Section 12.3B.2, if If Contractor fails to commence the Corrective Work (which commencement may include the detailed planning associated with the on-Site implementation of the Corrective Work) within a reasonable period of time not to exceed [***] five ([***]5) Business Days after Contractor’s receipt of written notice from Owner Days, or does not diligently perform complete such Corrective Work on an expedited basis (provided that Contractor’s timeline for performance shall be extended to the extent that Contractor is not provided reasonable access to those portions of the Train 4 Facility or the Phase 1 Facilities that have achieved Substantial Completion so that Contractor may commence, continue and complete the Corrective Work)basis, then Owner, upon by written notice to Contractor, may, as its sole and exclusive remedy for the Defect may (except for its right in addition to enforce Contractor’s indemnification obligations any other remedies that it has under this Agreement) perform such the Corrective Work, and Contractor shall be liable to Owner for all reasonable costs and expenses in excess of the GMP incurred by Owner in connection with such Corrective Work and arising out of or relating to such Defective Work and, if such costs exceed the GMP shall pay Owner (directly, by offset offset, or by collection on the Letter of Credit, at Owner’s sole discretion) ), an amount equal to such costs and expenses; or 2. If any provided, however, if such Defective Work (i) materially affects Train’s 1, Train 2’s, Train 3’s the operation or Train 4’s production use of any of the Project or loading capabilities and would put the Train 4 Facility at risk of being unable to operate or (ii) presents an imminent threat to the safety or health of any Person and Owner knows of such Defective Work, Owner may (in addition to any other remedies that it has under this Agreement) perform the such Corrective Work without giving prior written notice to Contractor (provided that Owner shall give advise Contractor notice of such event action as soon as reasonably possible after becoming aware of such Defective Workpossible), and, in that event, such eventwork shall be charged against the GMP until the GMP is reached, and thereafter such costs shall be at the expense of Contractor. If Owner incurs any costs for such work in excess of the GMP, Contractor shall be liable to Owner for all reasonable costs and expenses incurred by Owner in connection with such Corrective Work and shall immediately pay Owner (directly, by offset offset, or by collection on the Letter of Credit, at Owner’s sole discretion) an amount equal to such ), all reasonable costs and expenses (which incurred by Owner in excess of the GMP in performing such Work. Upon Contractor’s request, Owner shall provide documentation identifying the costs and expenses shall be adequately documented and supported by Owner). If Corrective Work is performed by Owner on Defective Work without providing any advance notice to Contractor, then Contractor’s obligations to perform Corrective Work on complete such Defective Work shall no longer apply to such Defective Work (it being understood that, at Contractor’s cost, and in Owner’s sole discretion, Owner may be able to obtain a replacement warranty from a third-party with respect to such item of Defective Work), provided that Contractor’s obligations under this Agreement with respect to all other portions of the Train 4 Facility (including an portion of Equipment) shall continue in full force and effect, including continuing in full force and effect with respect to any portions of the item of the same Equipment or portion of the Train 4 Facility in which Owner performed the Corrective Work (except for the specific Defect being addressed).

Appears in 1 contract

Sources: Turnkey Agreement (Global Clean Energy Holdings, Inc.)

Owner Right to Correct or Complete Defective Work. 1. (i) After Substantial CompletionCompletion of the applicable Train, and during the Defect Correction Period, and subject to Section 12.3B.212.3B.2(ii), if Contractor fails to commence the Corrective Work (which commencement may include the detailed planning associated with the on-Site implementation of the Corrective Work) within a reasonable period of time not to exceed [***] ten ([***]10) Business Days after Contractor’s receipt of written notice from Owner Owner, or does not diligently perform such Corrective Work on an expedited basis (provided that Contractor’s timeline for performance shall be extended to the extent that (a) Contractor is not provided reasonable access to those portions of the Train 4 Stage 3 Facility or the Phase 1 Facilities that have achieved Substantial Completion or (b) Owner has failed to de-energize and de-pressurize the applicable Equipment, so that Contractor may commence, continue and complete the Corrective Work), then Owner, upon written notice to Contractor, may, may (as its sole and exclusive remedy for the Defect (except for its right to enforce Contractor’s indemnification obligations under this Agreement) perform such Corrective Work, and Contractor shall be liable to Owner for all reasonable costs and expenses incurred by Owner in connection with such Corrective Work and shall pay Owner (directly, by offset or by collection on the Letter of Credit, at Owner’s sole discretion) an amount equal to such reasonable costs and expenses; orexpenses (which costs and expenses shall be adequately documented and supported by Owner). 2. (ii) If after Substantial Completion of the applicable Train, any Defective Work (ia) materially affects Train’s Train 1’s, Train 2’s, Train 3’s, Train 4’s, Train 5’s, Train 6’s or Train 47’s production or loading capabilities and would put the Train 4 Stage 3 Facility at risk of being unable to operate or (iib) presents an imminent threat to the safety or health of any Person and Owner knows of such Defective Work, Owner may (in addition to any other remedies that it has under this Agreement) perform the Corrective Work without giving prior notice opportunity to perform Corrective Work to Contractor (provided that Owner shall give Contractor notice of such event as soon as reasonably possible after becoming aware of such Defective Work), and, in such event, Contractor shall be liable to Owner for all reasonable costs and expenses incurred by Owner in connection with such Corrective Work and shall pay Owner (directly, by offset or by collection on the Letter of Credit, at Owner’s sole discretion) an amount equal to such reasonable costs and expenses (which costs and expenses shall be adequately documented and supported by Owner). If Corrective Work is performed by Owner on Defective Work without providing any advance notice and opportunity to perform Corrective Work to Contractor, then Contractor’s obligations to perform Corrective Work on such Defective Work shall no longer apply to such Defective Work (it being understood that, at Contractor’s cost, and in Owner’s sole discretion, Owner may be able to obtain a replacement warranty from a third-party with respect to such item of Defective Work), provided that Contractor’s obligations under this Agreement with respect to all other portions of the Train 4 Stage 3 Facility (including an any portion of Equipment) shall continue in full force and effect, including continuing in full force and effect with respect to any portions of the item of the same Equipment or portion of the Train 4 Stage 3 Facility in which Owner performed the Corrective Work (except for the specific Defect being addressedaddressed or further defects cause by the Corrective Work).

Appears in 1 contract

Sources: Fixed Price Separated Turnkey Agreement (Cheniere Energy, Inc.)

Owner Right to Correct or Complete Defective Work. 1. After Substantial Completion, and during the Defect Correction Period, and subject to Section 12.3B.2, if Contractor fails to commence the Corrective Work (which commencement may include the detailed planning associated with the on-Site implementation of the Corrective Work) within a reasonable period of time not to exceed [***] ([***]) Business Days after Contractor’s receipt of written notice from Owner or does not diligently perform such Corrective Work on an expedited basis (provided that Contractor’s timeline for performance shall be extended to the extent that Contractor is not provided reasonable access to those portions of the Train 4 3 Liquefaction Facility or the Phase Trains 1 Facilities and 2 Liquefaction Facility that have achieved Substantial Completion so that Contractor may commence, continue and complete the Corrective Work), then Owner, upon written notice to Contractor, may, may (as its sole and exclusive remedy for the Defect (except for its right to enforce Contractor’s indemnification obligations under this the Agreement) perform such Corrective Work, and Contractor shall be liable to Owner for all reasonable costs and expenses incurred by Owner in connection with such Corrective Work and shall pay Owner (directly, by offset or by collection on the Letter of Credit, at Owner’s sole discretion) an amount equal to such costs and expenses; or 2. If any Defective Work (i) materially affects Train’s 1, Train 2’s, Train 3’s or Train 43’s production or loading capabilities and would put the Train 4 3 Liquefaction Facility at risk of being unable to operate or (ii) presents an imminent threat to the safety or health of any Person and Owner knows of such Defective Work, Owner may (in addition to any other remedies that it has under this Agreement) perform the Corrective Work without giving prior notice to Contractor (provided that Owner shall give Contractor notice of such event as soon as reasonably possible after becoming aware of such Defective Work), and, in such event, Contractor shall be liable to Owner for all reasonable costs and expenses incurred by Owner in connection with such Corrective Work and shall pay Owner (directly, by offset or by collection on the Letter of Credit, at Owner’s sole discretion) an amount equal to such costs and expenses (which costs and expenses shall be adequately documented and supported by Owner). If Corrective Work is performed by Owner on Defective Work without providing any advance notice to Contractor, then Contractor’s obligations to perform Corrective Work on such Defective Work shall no longer apply to such Defective Work (it being understood that, at Contractor’s cost, and in Owner’s sole discretion, Owner may be able to obtain a replacement warranty from a third-party with respect to such item of Defective Work), provided that Contractor’s obligations under this Agreement with respect to all other portions of the Train 4 3 Liquefaction Facility (including an portion of Equipment) shall continue in full force and effect, including continuing in full force and effect with respect to any portions of the item of the same Equipment or portion of the Train 4 3 Liquefaction Facility in which Owner performed the Corrective Work (except for the specific Defect being addressed).

Appears in 1 contract

Sources: Fixed Price Turnkey Agreement (NextDecade Corp.)

Owner Right to Correct or Complete Defective Work. 1. After Substantial Completion, and during the Defect Correction Period, and subject to Section 12.3B.2, if Contractor fails to commence the Corrective Work (which commencement may include the detailed planning associated with the on-Site implementation of the Corrective Work) within a reasonable period of time not to exceed [***] ([***]) Business Days after Contractor’s receipt of written notice from Owner or does not diligently perform such Corrective Work on an expedited basis (provided that Contractor’s timeline for performance shall be extended to the extent that Contractor is not provided reasonable access to those portions of the Train 4 Facility or the Phase 1 Facilities that have achieved Substantial Completion so that Contractor may commence, continue and complete the Corrective Work), then Owner, upon written notice to Contractor, may, as its sole and exclusive remedy for the Defect (except for its right to enforce Contractor’s indemnification obligations under this Agreement) perform such Corrective Work, and Contractor shall be liable to Owner for all reasonable costs and expenses incurred by Owner in connection with such Corrective Work and shall pay Owner (directly, by offset or by collection on the Letter of Credit, at Owner’s sole discretion) an amount equal to such costs and expenses; or or 2. If any Defective Work (i) materially affects Train’s 1, Train 2’s, Train 3’s or Train 4’s production or loading capabilities and would put the Train 4 Facility at risk of being unable to operate or (ii) presents an imminent threat to the safety or health of any Person and Owner knows of such Defective Work, Owner may (in addition to any other remedies that it has under this Agreement) perform the Corrective Work without giving prior notice to Contractor (provided that Owner shall give Contractor notice of such event as soon as reasonably possible after becoming aware of such Defective Work), and, in such event, Contractor shall be liable to Owner for all reasonable costs and expenses incurred by Owner in connection with such Corrective Work and shall pay Owner (directly, by offset or RGLNG T4 – ▇▇▇▇▇▇▇ – Train 4 Amended and Restated EPC Agreement 97 Exhibit 10.1 by collection on the Letter of Credit, at Owner’s sole discretion) an amount equal to such costs and expenses (which costs and expenses shall be adequately documented and supported by Owner). If Corrective Work is performed by Owner on Defective Work without providing any advance notice to Contractor, then Contractor’s obligations to perform Corrective Work on such Defective Work shall no longer apply to such Defective Work (it being understood that, at Contractor’s cost, and in Owner’s sole discretion, Owner may be able to obtain a replacement warranty from a third-party with respect to such item of Defective Work), provided that Contractor’s obligations under this Agreement with respect to all other portions of the Train 4 Facility (including an portion of Equipment) shall continue in full force and effect, including continuing in full force and effect with respect to any portions of the item of the same Equipment or portion of the Train 4 Facility in which Owner performed the Corrective Work (except for the specific Defect being addressed).

Appears in 1 contract

Sources: Fixed Price Turnkey Agreement (NextDecade Corp)

Owner Right to Correct or Complete Defective Work. 1. After Substantial Completion, and during the Defect Correction Period, and subject to Section 12.3B.2, if Contractor fails to commence the Corrective Work (which commencement may include the detailed planning associated with the on-Site implementation of the Corrective Work) within a reasonable period of time not to exceed [***] ([***]) Business Days after Contractor’s receipt of written notice from Owner or does not diligently perform such Corrective Work on an expedited basis (provided that Contractor’s timeline for performance shall be extended to the extent that Contractor is not provided reasonable access to those portions of the Train 5 Facility, Train 4 Facility or the Phase 1 Facilities that have achieved Substantial Completion so that Contractor may commence, continue and complete the Corrective Work), then Owner, upon written notice to Contractor, may, as its sole and exclusive remedy for the Defect (except for its right to enforce Contractor’s indemnification obligations under this Agreement) perform such Corrective Work, and Contractor shall be liable to Owner for all reasonable costs and expenses incurred by Owner in connection with such Corrective Work and shall pay Owner (directly, by offset or by collection on the Letter of Credit, at Owner’s sole discretion) an amount equal to such costs and expenses; or or 2. If any Defective Work (i) materially affects Train’s 1, Train 2’s, Train 3’s, Train 4’s or Train 45’s production or loading capabilities and would put the Train 4 5 Facility at risk of being unable to operate or (ii) presents an imminent threat to the safety or health of any Person and Owner knows of such Defective Work, Owner may (in addition to any other remedies that it has under this RGLNG T5 – ▇▇▇▇▇▇▇ – Train 5 EPC Agreement 97 Exhibit 10.2 Agreement) perform the Corrective Work without giving prior notice to Contractor (provided that Owner shall give Contractor notice of such event as soon as reasonably possible after becoming aware of such Defective Work), and, in such event, Contractor shall be liable to Owner for all reasonable costs and expenses incurred by Owner in connection with such Corrective Work and shall pay Owner (directly, by offset or by collection on the Letter of Credit, at Owner’s sole discretion) an amount equal to such costs and expenses (which costs and expenses shall be adequately documented and supported by Owner). If Corrective Work is performed by Owner on Defective Work without providing any advance notice to Contractor, then Contractor’s obligations to perform Corrective Work on such Defective Work shall no longer apply to such Defective Work (it being understood that, at Contractor’s cost, and in Owner’s sole discretion, Owner may be able to obtain a replacement warranty from a third-party with respect to such item of Defective Work), provided that Contractor’s obligations under this Agreement with respect to all other portions of the Train 4 5 Facility (including an portion of Equipment) shall continue in full force and effect, including continuing in full force and effect with respect to any portions of the item of the same Equipment or portion of the Train 4 5 Facility in which Owner performed the Corrective Work (except for the specific Defect being addressed).

Appears in 1 contract

Sources: Epc Agreement (NextDecade Corp)