Common use of OWNER’S RIGHT TO PERFORM CONSTRUCTION AND TO AWARD SEPARATE CONTRACTS Clause in Contracts

OWNER’S RIGHT TO PERFORM CONSTRUCTION AND TO AWARD SEPARATE CONTRACTS. § 7.4.1 The Owner reserves the right to perform construction or operations related to the Project with the Owner’s own forces, and to award separate contracts in connection with other portions of the Project. § 7.4.2 The Contractor shall coordinate and cooperate with the Owner’s own forces and separate contractors employed by the Owner. § 7.4.3 Costs caused by delays or by improperly timed activities or defective construction shall be borne by the party responsible therefor.

Appears in 18 contracts

Sources: Standard Form of Agreement Between Owner and Contractor for a Residential or Small Commercial Project, Standard Form of Agreement Between Owner and Contractor for a Residential or Small Commercial Project, Standard Form of Agreement Between Owner and Contractor for a Residential or Small Commercial Project

OWNER’S RIGHT TO PERFORM CONSTRUCTION AND TO AWARD SEPARATE CONTRACTS. § 7.4.1 2.4.1 The Owner reserves the right to perform construction or operations related to the Project project with the Owner’s own forces, and to award separate contracts in connection with other portions of the Projectproject. § 7.4.2 2.4.2 The Contractor shall coordinate and cooperate with the Owner’s own forces and separate contractors employed by the Owner. § 7.4.3 2.4.3 Costs caused by delays or by improperly timed activities or defective construction shall be borne by the party responsible therefor.

Appears in 1 contract

Sources: General Conditions of the Contract

OWNER’S RIGHT TO PERFORM CONSTRUCTION AND TO AWARD SEPARATE CONTRACTS. § 7.4.1 2.4.1 The Owner reserves the right to perform construction or operations related to the Project with the Owner’s own forces, and to award separate contracts in connection with other portions of the Project. § 7.4.2 2.4.2 The Contractor shall coordinate and cooperate with the Owner’s own forces and separate contractors employed by of the Owner. § 7.4.3 2.4.3 Costs caused by delays or by improperly timed activities or defective construction shall be borne by the party responsible therefor.

Appears in 1 contract

Sources: Contract Between Owner and Contractor for a Stipulated Sum

OWNER’S RIGHT TO PERFORM CONSTRUCTION AND TO AWARD SEPARATE CONTRACTS. § 7.4.1 The Owner reserves the right to perform construction or operations related to the Project with the Owner’s own forces, and to award separate contracts in connection with other portions of the Project.. all s vis ▇▇▇ ited the site, personal § 7.4.2 The Contractor shall coordinate and cooperate with the Owner’s own forces and separate contractors employed by the Owner. § 7.4.3 Costs caused by delays or by improperly timed activities or defective construction shall be borne by the party sh responsible therefor.

Appears in 1 contract

Sources: Standard Form of Agreement Between Owner and Contractor for a Residential or Small Commercial Project