Payment Extensions. In connection with Related Electric Power Services performed by BP under this Agreement, BP will be deemed to have provided to IDT an Invoice for immediate payment in respect of any payments made to the ISO. If funds on deposit in the Collateral Account are not sufficient to pay the amount of such Invoice, then BP shall, at IDT’s request, extend the payment date for such deficient amount for a period of 30 days after the extension is made (“Permitted Extension Period”) to the extent reasonably necessary to enable funds to be deposited into the Collateral Account to cover such deficient amount (any such payment extension, a “Payment Extension”). Table of Contents (a) Notwithstanding the foregoing, BP shall not be required to give any such Payment Extension if: (i) after giving effect to such Payment Extension, (A) a Collateral Requirement of IDT would arise under the Master Netting Agreement or (B) the total aggregate amount of Payment Extensions outstanding would exceed * to IDT under any POR Program; (ii) the insufficiency of funds in the Collateral Account is due to Customers that are not covered by a POR Program failing to make direct payments to IDT when due as of the date IDT requests the Payment Extension; (iii) such insufficiency of funds in the Collateral Account has been caused, or contributed to, by actions or inactions on the part of IDT or any Affiliates of IDT; or (iv) the conditions that must be satisfied prior to BP’s entering into any Direct Transaction have not been fulfilled to the satisfaction of, or have not been waived by, BP as of the date IDT requests such Payment Extension. (b) To the extent not reimbursed from future funds in the Collateral Account, IDT will pay all amounts subject to a Payment Extension in full on the last day of the applicable Permitted Extension Period. (c) All amounts subject to a Payment Extension shall bear interest from the original payment due date for the amount included in the Payment Extension until the date when the amount is paid in full at a per annum interest rate of LIBOR plus * basis points. Such accrued interest due on the Payment Extension amount shall be paid to BP on the earlier of the date on which the amount included in the Payment Extension is paid in full or the last day of the applicable Payment Extension Period. (d) Failure to pay the Payment Extension amount, including accrued interest, as and when due would constitute an Event of Default.
Appears in 3 contracts
Sources: Preferred Supplier Agreement (Genie Energy. Ltd.), Preferred Supplier Agreement (Idt Corp), Preferred Supplier Agreement (Idt Corp)
Payment Extensions. In connection with Related Electric Power Services performed by BP under this Agreement, BP will be deemed to have provided to IDT an Invoice for immediate payment in respect of any payments made to the ISO. If funds on deposit in the Collateral Account are not sufficient to pay the amount of such Invoice, then BP shall, at IDT’s request, extend the payment date for such deficient amount for a period of 30 days after the extension is made (“Permitted Extension Period”) to the extent reasonably necessary to enable funds to be deposited into the Collateral Account to cover such deficient amount (any such payment extension, a “Payment Extension”). Table of ContentsContents CONFIDENTIAL PORTIONS HAVE BEEN OMITTED FROM THIS DOCUMENT BASED UPON A REQUEST FOR CONFIDENTIAL TREATMENT PURSUANT TO RULE 24b-2 OF THE SECURITIES EXCHANGE ACT OF 1934 AND HAVE BEEN SEPARATELY FILED WITH THE SECURITIES AND EXCHANGE COMMISSION. THE LOCATION OF OMITTED TEXT IS INDICATED BY AN ASTERISK (*)
(a) Notwithstanding the foregoing, BP shall not be required to give any such Payment Extension if:
(i) after giving effect to such Payment Extension, (A) a Collateral Requirement of IDT would arise under the Master Netting Agreement or (B) the total aggregate amount of Payment Extensions outstanding would exceed * to IDT under any POR Program;
(ii) the insufficiency of funds in the Collateral Account is due to Customers that are not covered by a POR Program failing to make direct payments to IDT when due as of the date IDT requests the Payment Extension;
(iii) such insufficiency of funds in the Collateral Account has been caused, or contributed to, by actions or inactions on the part of IDT or any Affiliates of IDT; or
(iv) the conditions that must be satisfied prior to BP’s entering into any Direct Transaction have not been fulfilled to the satisfaction of, or have not been waived by, BP as of the date IDT requests such Payment Extension.
(b) To the extent not reimbursed from future funds in the Collateral Account, IDT will pay all amounts subject to a Payment Extension in full on the last day of the applicable Permitted Extension Period.
(c) All amounts subject to a Payment Extension shall bear interest from the original payment due date for the amount included in the Payment Extension until the date when the amount is paid in full at a per annum interest rate of LIBOR plus * basis points. Such accrued interest due on the Payment Extension amount shall be paid to BP on the earlier of the date on which the amount included in the Payment Extension is paid in full or the last day of the applicable Payment Extension Period.
(d) Failure to pay the Payment Extension amount, including accrued interest, as and when due would constitute an Event of Default.