Per Day Factor. 0.55 The Per Day Factor is determined based on the Potential for Harm and Deviation from Requirement scores using Table 3 in the 2017 Enforcement Policy. For a Moderate Potential for Harm and Major Deviation from Requirement, the Per Day Factor is 0.55.
Appears in 1 contract
Sources: Settlement Agreement
Per Day Factor. 0.55 0.35 The Per Day Factor is determined based on the Potential for Harm and Deviation from Requirement scores using Table 3 in the 2017 Enforcement Policy. For a Moderate Potential for Harm and Major Moderate Deviation from Requirement, the Per Day Factor is 0.550.35.
Appears in 1 contract
Sources: Settlement Agreement
Per Day Factor. 0.55 0.35 The Per Day Factor is determined based on the Potential for Harm and Deviation from Requirement scores using Table 3 in the 2017 Enforcement Policy. For a Moderate Minor Potential for Harm and Major Deviation from Requirement, the Per Day Factor is 0.550.35.
Appears in 1 contract
Sources: Settlement Agreement