Permitted Incomplete Work Defined. Permitted Incomplete Work is work that is incomplete through no fault of the Contractor, as determined by the Owner, including, but not limited to, seasonal test and balance, seasonal landscaping, scheduled elevator inspection or maintenance, incomplete work due to failure of Separate Contractors to complete work, and the like.
Appears in 41 contracts
Sources: Construction Contract, Construction Contract, Construction Contract
Permitted Incomplete Work Defined. Permitted Incomplete Work is work that is incomplete through no fault of the Contractor, as determined by the OwnerDesign-Builder, including, but not limited to, seasonal test and balance, seasonal landscaping, scheduled elevator inspection or maintenance, incomplete work due to failure of Separate Contractors to complete work, and the like.
Appears in 14 contracts
Sources: Design Build Contract, Design Build Contract, Design Build Contract
Permitted Incomplete Work Defined. Permitted Incomplete Work is work that is incomplete through no fault of the ContractorCM/GC, as determined by the Owner, including, but not limited to, seasonal test and balance, seasonal landscaping, scheduled elevator inspection or maintenance, incomplete work due to failure of Separate Contractors to complete work, and the like.
Appears in 3 contracts
Sources: Construction Management Agreement, Construction Management Agreement, Construction Management Agreement
Permitted Incomplete Work Defined. Permitted Incomplete Work is work that is incomplete through no fault of the ContractorDesign-Builder, as determined by the Owner, including, but not limited to, seasonal test and balance, seasonal landscaping, scheduled elevator inspection or maintenance, incomplete work due to failure of Separate Contractors to complete work, and the like.
Appears in 2 contracts
Sources: Design Build Contract, Construction Contract
Permitted Incomplete Work Defined. Permitted Incomplete Work is work that is incomplete through no fault of the Contractor, as determined by the Owner, including, but not limited to, HVAC seasonal test and balancebalance (See Section 6.4.7), seasonal landscapinglandscaping or maintenance, scheduled elevator elevator/escalator inspection or maintenance, incomplete work due to failure of Separate Contractors to complete work, and the like.
Appears in 1 contract
Permitted Incomplete Work Defined. Permitted Incomplete Work is work that is incomplete through no fault of the ContractorCM/GC, as determined by the Owner, including, but not limited to, HVAC seasonal test and balancebalance (See Section 6.4.7), seasonal landscapinglandscaping or maintenance, scheduled elevator elevator/escalator inspection or maintenance, incomplete work due to failure of Separate Contractors to complete work, and the like.
Appears in 1 contract
Sources: Construction Management Agreement