Phase I Notice. Contractor shall give Owner and the Owner Engineer at least 10 Business Days’ advance Notice of the date on which Contractor intends to commence the initial Phase I Performance Tests to determine Phase I Substantial Completion. Thereafter, Contractor shall give Owner and the Owner Engineer at least 5 Business Days’ advance Notice of all subsequent Phase I Performance Tests, unless a shorter notice period is agreed to in advance and in writing by Owner. Contractor shall notify Owner and the Owner Engineer of such Phase I Performance Tests so that they may be present or represented to witness and monitor all aspects of such tests.
Appears in 2 contracts
Sources: Engineering, Procurement and Construction Agreement (Ada-Es Inc), Engineering, Procurement and Construction Agreement (Ada-Es Inc)