Phasor Measurement Units. An Interconnection Customer shall install and maintain, at its expense, phasor measurement units (“PMUs”) if it meets the following criteria: (1) completed a Class Year Study or Cluster Study after Class Year 2017; and (2) proposes a new Facility that either (a) has a maximum net output equal to or greater than 100 MW or (b) requires, as Attachment Facilities or System Upgrade Facilities, a new substation of 230kV or above. PMUs shall be installed on the Facility on the low side of the generator step-up transformer, unless it is a non-synchronous generation facility, in which case the PMUs shall be installed on the Interconnection Customer side of the Point of Interconnection. The PMUs must be capable of performing phasor measurements at a minimum of 60 samples per second which are synchronized via a high-accuracy satellite clock. To the extent Interconnection Customer installs similar quality equipment, such as relays or digital fault recorders, that can collect data at least at the same rate as PMUs and which data is synchronized via a high-accuracy satellite clock, such equipment would satisfy this requirement. Interconnection Customer shall be required to install and maintain, at its expense, PMU equipment which includes the communication circuit capable of carrying the PMU data to a local data concentrator, and then transporting the information continuously to the Connecting Transmission Owner and the NYISO; as well as store the PMU data locally for thirty (30) Calendar Days. Interconnection Customer shall provide to Connecting Transmission Owner and the NYISO all necessary and requested information through the Connecting Transmission Owner’s and the NYISO’s synchrophasor system, including the following: (a) ▇▇▇▇▇ ▇▇ and MVAR measured at the Interconnection Customer side of the generator step-up transformer (or, for a non-synchronous generation facility, to be measured at the Interconnection Customer side of the Point of Interconnection); (b) generator terminal voltage and current magnitudes and angles; (c) generator terminal frequency and frequency rate of change; and (d) generator field voltage and current, where available; and (e) breaker status, if available. The Connecting Transmission Owner will provide for the ongoing support and maintenance of the network communications linking the data concentrator to the Connecting Transmission Owner and the NYISO, consistent with ISO Procedures detailing the obligations related to SCADA data.
Appears in 6 contracts
Sources: Standard Interconnection Agreement, Standard Interconnection Agreement, Engineering & Procurement Agreement
Phasor Measurement Units. An Interconnection Customer A Developer or the Connecting Transmission Owner shall install and maintaininstall, at its Developer’s expense, a phasor measurement units unit (“PMUsPMU”) if it the Developer meets the following criteria: (1) completed a Class Year Study or Cluster Study after Class Year 2017; and (2) proposes a new Large Facility that either either
(a) has a maximum net output equal to or greater than 100 MW or (b) requires, as Attachment Facilities or System Upgrade Facilities, a new substation of 230kV or above. PMUs The PMU shall be installed on the Facility on the low side of the generator step-up transformer, unless it is a non-synchronous generation facility, in which case the PMUs shall be installed on the Interconnection Customer high side of the Point of Interconnection. The PMUs PMU must be capable of performing phasor measurements at a minimum of 60 samples per second which are synchronized via a high-accuracy satellite clock. To the extent Interconnection Customer Developer or Connecting Transmission Owner installs similar quality equipment, such as relays or digital fault recorders, that can collect data at least at the same rate as PMUs and which data is synchronized via a high-accuracy satellite clock, such equipment would satisfy this requirement. Interconnection Customer Developer or Connecting Transmission Owner shall be required to install and maintaininstall, at its Developer’s expense, PMU equipment equipment, which includes the communication circuit capable of carrying the PMU data to a local data concentrator, and then transporting the information continuously to the Connecting Transmission Owner’s data concentrator. Connecting Transmission Owner and the NYISO; as well as will store the PMU data locally for thirty (30) Calendar Daysdays. Interconnection Customer The Developer’s and Connecting Transmission Owner’s responsibilities concerning the PMU and PMU equipment shall provide be set forth in Appendix A to this Agreement. Connecting Transmission Owner and shall provide the NYISO all necessary and requested information through the Connecting Transmission Owner’s its and the NYISO’s synchrophasor system, including the following: (a) ▇▇▇▇▇ ▇▇ and MVAR measured at the Interconnection Customer side of the generator step-up transformer (or, for a non-synchronous generation facility, to be measured at the Interconnection Customer high side of the Point of Interconnection); (b) generator terminal voltage and current magnitudes and anglesangles at the high side of the Point of Interconnection; (c) generator terminal frequency and frequency rate of changechange at the high side of the Point of Interconnection; and (d) generator field voltage and current, where available; and (e) breaker status, if available. The Connecting Transmission Owner will provide for the ongoing support and maintenance of the network communications linking the its data concentrator to the Connecting Transmission Owner and the NYISO, consistent with ISO Procedures detailing the obligations related to SCADA data.
Appears in 6 contracts
Sources: Merchant Transmission Facility Interconnection Agreement, Interconnection Agreement, Merchant Transmission Facility Interconnection Agreement
Phasor Measurement Units. An A Interconnection Customer shall cause KIAC to install and maintain, at its expense, phasor measurement units (“PMUs”) if it meets the following criteria: (1) completed a Class Year Study or Cluster Study after Class Year 2017; and (2) proposes a new Large Facility that either (a) has a maximum net output equal to or greater than 100 MW or (b) requires, as Attachment Facilities or System Upgrade Facilities, a new substation of 230kV or above. PMUs shall be installed on the Large Facility on the low side of the generator step-up transformer, unless it is a non-synchronous generation facility, in which case the PMUs shall be installed on the Interconnection Customer side of the Point of Interconnection. The PMUs must be capable of performing phasor measurements at a minimum of 60 samples per second which are synchronized via a high-accuracy satellite clock. To the extent Interconnection Customer installs similar quality equipment, such as relays or digital fault recorders, that can collect data at least at the same rate as PMUs and which data is synchronized via a high-accuracy satellite clock, such equipment would satisfy this requirement. Interconnection Customer shall be required cause KIAC to install and maintain, at its expense, PMU equipment which includes the communication circuit capable of carrying the PMU data to a local data concentrator, and then transporting the information continuously to the Connecting Transmission Owner and the NYISO; as well as store the PMU data locally for thirty (30) Calendar Daysdays. Interconnection Customer shall cause KIAC to provide to Connecting Transmission Owner and the NYISO all necessary and requested information through the Connecting Transmission Owner’s and the NYISO’s synchrophasor system, including the following: (a) ▇▇▇▇▇ ▇▇ and MVAR measured at the Interconnection Customer side of the generator step-up transformer (or, for a non-synchronous generation facility, to be measured at the Interconnection Customer side of the Point of Interconnection); (b) generator terminal voltage and current magnitudes and angles; (c) generator terminal frequency and frequency rate of change; and (d) generator field voltage and current, where available; and (e) breaker status, if available. The Connecting Transmission Owner will provide for the ongoing support and maintenance of the network communications linking the data concentrator to the Connecting Transmission Owner and the NYISO, consistent with ISO Procedures detailing the obligations related to SCADA data.
Appears in 5 contracts
Sources: Interconnection Agreement, Interconnection Agreement, Interconnection Agreement
Phasor Measurement Units. An Interconnection Customer Con Edison shall install and maintain, at its expense, phasor measurement units (“PMUs”) if it meets the following criteria: (1) completed a Class Year Study or Cluster Study after Class Year 2017; and (2) proposes a new Large Facility that either (a) has a maximum net output equal to or greater than 100 MW or (b) requires, as Attachment Facilities or System Upgrade Facilities, a new substation of 230kV or above. PMUs shall be installed on the Large Facility on the low side of the generator step-up transformer, unless it is a non-synchronous generation facility, in which case the PMUs shall be installed on the Interconnection Customer Con Edison side of the Point of Interconnection. The PMUs must be capable of performing phasor measurements at a minimum of 60 samples per second which are synchronized via a high-accuracy satellite clock. To the extent Interconnection Customer Con Edison installs similar quality equipment, such as relays or digital fault recorders, that can collect data at least at the SERVICE AGREEMENT NO. 2520 same rate as PMUs and which data is synchronized via a high-accuracy satellite clock, such equipment would satisfy this requirement. Interconnection Customer Con Edison shall be required to install and maintain, at its expense, PMU equipment which includes the communication circuit capable of carrying the PMU data to a local data concentrator, and then transporting the information continuously to the Connecting Transmission Owner and the NYISO; as well as store the PMU data locally for thirty (30) Calendar Daysdays. Interconnection Customer Con Edison shall provide to Connecting Transmission Owner and the NYISO all necessary and requested information through the Connecting Transmission OwnerCon Edison’s and the NYISO’s synchrophasor system, including the following: (a) ▇▇▇▇▇ ▇▇ and MVAR measured at the Interconnection Customer Large Generating Facility side of the generator step-up transformer (or, for a non-synchronous generation facility, to be measured at the Interconnection Customer Large Generating Facility side of the Point of Interconnection); (b) generator terminal voltage and current magnitudes and angles; (c) generator terminal frequency and frequency rate of change; and (d) generator field voltage and current, where available; and (e) breaker status, if available. The Connecting Transmission Owner Con Edison will provide for the ongoing support and maintenance of the network communications linking the data concentrator to the Connecting Transmission Owner and the NYISO, consistent with ISO Procedures detailing the obligations related to SCADA data.
Appears in 3 contracts
Sources: Interconnection Agreement, Interconnection Agreement, Interconnection Agreement
Phasor Measurement Units. An Interconnection Customer A DeveloperCon Edison shall install and maintain, at its expense, phasor measurement units (“PMUs”) if it meets the following criteria: (1) completed a Class Year Study or Cluster Study after Class Year 2017; and (2) proposes a new Large Facility that either (a) has a maximum net output equal to or greater than 100 MW or (b) requires, as Attachment Facilities or System Upgrade Facilities, a new substation of 230kV or above. PMUs shall be installed on the Large Facility on the low side of the generator step-up transformer, unless it is a non-synchronous generation facility, in which case the PMUs shall be installed on the Interconnection Customer DeveloperCon Edison side of the Point of Interconnection. The PMUs must be capable of performing phasor measurements at a minimum of 60 samples per second which are synchronized via a high-accuracy satellite clock. To the extent Interconnection Customer DeveloperCon Edison installs similar quality equipment, such as relays or digital fault recorders, that can collect data at least at the same rate as PMUs and which data is synchronized via a high-accuracy satellite clock, such equipment would satisfy this requirement. Interconnection Customer DeveloperCon Edison shall be required to install and maintain, at its expense, PMU equipment which includes the communication circuit capable of carrying the PMU data to a local data concentrator, and then transporting the information continuously to the Connecting Transmission Owner and the NYISO; as well as store the PMU data locally for thirty (30) Calendar Daysdays. Interconnection Customer DeveloperCon Edison shall provide to Connecting Transmission Owner and the NYISO all necessary and requested information through the Connecting Transmission OwnerOwner’sCon Edison’s and the NYISO’s synchrophasor system, including the following: (a) ▇▇▇▇▇ ▇▇ and MVAR measured at the Interconnection Customer DeveloperLarge Generating Facility side of the generator step-up transformer (or, for a non-synchronous generation facility, to be measured at the Interconnection Customer DeveloperLarge Generating Facility side of the Point of Interconnection); (b) generator terminal voltage and current magnitudes and angles; (c) generator terminal frequency and frequency rate of change; and (d) generator field voltage and current, where available; and (e) breaker status, if available. The Connecting Transmission Owner will provide for the ongoing support and maintenance of the network communications linking the data concentrator to the Connecting Transmission Owner and the NYISO, consistent with ISO Procedures detailing the obligations related to SCADA data.and
Appears in 2 contracts
Sources: Standard Large Generator Interconnection Agreement, Standard Large Generator Interconnection Agreement
Phasor Measurement Units. An Interconnection Customer A Developer or the Connecting Transmission Owner shall install and maintain, at its itsDeveloper’s expense, a phasor measurement units unitsunit (“PMUsPMUsPMU”) if it itthe Developer meets the following criteria: (1) completed a Class Year Study or Cluster Study after Class Year 2017; and (2) proposes a new Large Facility that either (a) has a maximum net output equal to or greater than 100 MW or (b) requires, as Attachment Facilities or System Upgrade Facilities, a new substation of 230kV or above. PMUs PMUsThe PMU shall be installed on the Large Facility on the low side of the generator step-up transformer, unless it is a non-synchronous generation facility, in which case the PMUs shall be installed on the Interconnection Customer Developerhigh side of the Point of Interconnection. The PMUs PMUsPMU must be capable of performing phasor measurements at a minimum of 60 samples per second which are synchronized via a high-accuracy satellite clock. To the extent Interconnection Customer Developer or Connecting Transmission Owner installs similar quality equipment, such as relays or digital fault recorders, that can collect data at least at the same rate as PMUs and which data is synchronized via a high-accuracy satellite clock, such equipment would satisfy this requirement. Interconnection Customer Developer or Connecting Transmission Owner shall be required to install and maintain, at its itsDeveloper’s expense, PMU equipment equipment, which includes the communication circuit capable of carrying the PMU data to a local data concentrator, and then transporting the information continuously to the Connecting Transmission Owner and the NYISO; as well as asOwner’s data concentrator. Connecting Transmission Owner will store the PMU data locally for thirty (30) Calendar Daysdays. Interconnection Customer Developer shall provide to The Developer’s and Connecting Transmission Owner’s responsibilities concerning the PMU and PMU equipment shall be set forth in Appendix A to this Agreement. Connecting Transmission Owner and andshall provide the NYISO all necessary and requested information through the Connecting Transmission Owner’s Owner’sits and the NYISO’s synchrophasor system, including the following: (a) ▇▇▇▇▇ ▇▇ and MVAR measured at the Interconnection Customer Developer side of the generator step-up transformer (or, for a non-synchronous generation facility, to be measured at the Interconnection Customer Developerhigh side of the Point of Interconnection); (b) generator terminal voltage and current magnitudes and anglesangles at the high side of the Point of Interconnection; (c) generator terminal frequency and frequency rate of change; and (d) generator field voltage and current, where available; and (e) breaker status, if available. The Connecting Transmission Owner will provide for the ongoing support and maintenance of the network communications linking the data concentrator to the Connecting Transmission Owner and the NYISO, consistent with ISO Procedures detailing the obligations related to SCADA data.and
Appears in 1 contract
Phasor Measurement Units. An Interconnection Customer Con Edison shall install and maintain, at its expense, phasor measurement units (“PMUs”) if it meets the following criteria: (1) completed a Class Year Study or Cluster Study after Class Year 2017; and (2) proposes a new Large Facility that either (a) has a maximum net output equal to or greater than 100 MW or (b) requires, as Attachment Facilities or System Upgrade Facilities, a new substation of 230kV or above. PMUs shall be installed on the Large Facility on the low side of the generator step-up transformer, unless it is a non-synchronous generation facility, in which case the PMUs shall be installed on the Interconnection Customer Con Edison side of the Point of Interconnection. The PMUs must be capable of performing phasor measurements at a minimum of 60 samples per second which are synchronized via a high-accuracy satellite clock. To the extent Interconnection Customer Con Edison installs similar quality equipment, such as relays or digital fault recorders, that can collect data at least at the 22 SERVICE AGREEMENT NO. 2521 same rate as PMUs and which data is synchronized via a high-accuracy satellite clock, such equipment would satisfy this requirement. Interconnection Customer Con Edison shall be required to install and maintain, at its expense, PMU equipment which includes the communication circuit capable of carrying the PMU data to a local data concentrator, and then transporting the information continuously to the Connecting Transmission Owner and the NYISO; as well as store the PMU data locally for thirty (30) Calendar Daysdays. Interconnection Customer Con Edison shall provide to Connecting Transmission Owner and the NYISO all necessary and requested information through the Connecting Transmission OwnerCon Edison’s and the NYISO’s synchrophasor system, including the following: (a) ▇▇▇▇▇ ▇▇ and MVAR measured at the Interconnection Customer Large Generating Facility side of the generator step-up transformer (or, for a non-synchronous generation facility, to be measured at the Interconnection Customer Large Generating Facility side of the Point of Interconnection); (b) generator terminal voltage and current magnitudes and angles; (c) generator terminal frequency and frequency rate of change; and (d) generator field voltage and current, where available; and (e) breaker status, if available. The Connecting Transmission Owner Con Edison will provide for the ongoing support and maintenance of the network communications linking the data concentrator to the Connecting Transmission Owner and the NYISO, consistent with ISO Procedures detailing the obligations related to SCADA data.
Appears in 1 contract
Sources: Interconnection Agreement