Planned Works. 8.1 The Maximum Delivery Rate shall be reduced during the Maintenance Period. Subject to clause 8.5, the Maintenance Period shall have a maximum duration of forty-five (45) calendar days. 8.2 The Service Provider shall use all reasonable endeavours to minimise the duration of the Maintenance Period. 8.3 In addition, the Service shall be completely or partially unavailable to NGG on Gasdays when National Grid Gas is carrying out maintenance to the NTS such that (as a result of such maintenance) Natural Gas cannot be delivered from the Terminal at the Gas Delivery Point. 8.4 The Service Provider shall use all reasonable endeavours to schedule the Maintenance Period at the same time as any maintenance of the NTS planned by National Grid Gas which would result in Natural Gas being unable to be delivered from the Terminal at the Gas Delivery Point. 8.5 The Service Provider may amend the Maintenance Period by giving NGG reasonable prior written notice which shall in any event be given not later than the date being one month prior to the start date of the proposed Maintenance Period, provided that the Storage Operator shall not (without the prior written agreement of NGG) be entitled to amend the Maintenance Period such that its duration is greater than forty-five (45) calendar days. 8.6 The Service Fee shall not apply on Gasdays when the Maximum Delivery Rate is reduced pursuant to Clause 8.1 or the Service is otherwise completely or partially unavailable pursuant to Clause 8.3.

Appears in 2 contracts

Sources: Operating Margins Services Agreement, Operating Margins Services Agreement

Planned Works. 8.1 The Maximum Delivery Rate shall be reduced during the Maintenance Period. Subject to clause 8.5, the Maintenance Period shall have a maximum duration of forty-five (45) calendar days. 8.2 The Service Provider shall use all reasonable endeavours to minimise the duration of the Maintenance Period. 8.3 In addition, the Service shall be completely or partially unavailable to NGG on Gasdays when National Grid Gas is carrying out maintenance to the NTS such that (as a result of such maintenance) Natural Gas cannot be delivered from the Terminal at the Gas Delivery Point. 8.4 The Service Provider shall use all reasonable endeavours to schedule the Maintenance Period at the same time as any maintenance of the NTS planned by National Grid Gas which would result in Natural Gas being unable to be delivered from the Terminal at the Gas Delivery Point. 8.5 The Service Provider may amend the Maintenance Period by giving NGG reasonable prior written notice which shall in any event be given not later than the date being one month prior to the start date of the proposed Maintenance Period, provided that the Storage Operator Service Provider shall not (without the prior written agreement of NGG) be entitled to amend the Maintenance Period such that its duration is greater than forty-five (45) calendar days. 8.6 The Service Fee shall not apply on Gasdays when the Maximum Delivery Rate is reduced pursuant to Clause 8.1 or the Service is otherwise completely or partially unavailable pursuant to Clause 8.3.

Appears in 1 contract

Sources: Gas Delivery Services Agreement