Post Construction. 9.1 Architect shall, accompanied by a representative of Owner, make at least three (3) complete inspections of the Work after the final completion thereof. One such inspection shall be made approximately three (3) months after the final completion of the Work, the second at twelve (12) months and the third at twenty-three (23) months after final completion of the Work. Architect shall be responsible to coordinate such inspections. 9.2 At each such inspection, Architect shall thoroughly examine the Work to confirm that all portions thereof are in accordance with the Construction Documents. Architect shall promptly deliver written reports of these inspections to Owner. Such reports shall describe in detail any deviations of the Work from the Construction Documents and any evidence of defects or potential defects in the Work observed by Architect. 9.3 Architect shall inspect any remedial work performed by the Contractor and confirm in writing to Owner that such remedial work has been completed.
Appears in 1 contract
Sources: Architect Agreement
Post Construction. 9.1 Architect shall, accompanied by a representative of Owner, make at least three (3) complete inspections of the Work after the final completion thereof. One such inspection shall be made approximately three (3) months after the final completion of the Work, the second at twelve (12) months and the third at twenty-three (23) months after final completion of the Work. Architect shall be responsible to coordinate such inspections.
9.2 . At each such inspection, Architect shall thoroughly examine the Work to confirm that all portions thereof are in accordance with the Construction Documents. Architect shall promptly deliver written reports of these inspections to Owner. Such reports shall describe in detail any deviations of the Work from the Construction Documents and any evidence of defects or potential defects in the Work observed by Architect.
9.3 . Architect shall inspect any remedial work performed by the Contractor and confirm in writing to Owner that such remedial work has been completed.
Appears in 1 contract
Sources: Architect Agreement