Power Factor Design Criteria. Interconnection Customer shall design the Generating Facility to maintain a composite power delivery at continuous rated power output at the Point of Interconnection at a power factor within the range of 0.95 leading to 0.95 lagging, unless Distribution Provider has established different requirements that apply to all generators in the Control Area on a comparable basis. The requirements of this paragraph shall not apply to wind generators; rather, the requirements of Appendix H shall apply to wind generators.
Appears in 1 contract
Sources: Generator Interconnection Agreement
Power Factor Design Criteria. Interconnection Customer shall design the Generating Facility to maintain be capable of maintaining a composite power delivery at continuous rated power output at the Point of Interconnection at a all power factor within the range of factors over 0.95 leading to 0.95 lagging, unless Distribution Transmission Provider has established different requirements that apply to all generators in the Control Area Local Balancing Authority on a comparable acomparable basis. The applicable Local Balancing Authority power factor requirements of this paragraph shall not apply to wind generators; rather, are listed on the requirements of Appendix H shall apply to wind generators.Transmission Provider’s website at
Appears in 1 contract
Sources: Generator Interconnection Agreement
Power Factor Design Criteria. Interconnection Customer shall design the Generating Qualifying Facility to maintain a composite power delivery at continuous rated power output at the Point of Interconnection at a power factor within the range of 0.95 leading to 0.95 lagging, unless Distribution Provider the Company has established different requirements that apply to all synchronous generators in the Control Area on a comparable basis. The requirements of this paragraph shall not apply to wind generators; rather, the requirements of Appendix H shall apply to wind generators.generators.
Appears in 1 contract
Sources: Qualifying Facility Transmission Interconnection Agreement
Power Factor Design Criteria. Interconnection Customer shall design the Large Generating Facility to maintain a composite power delivery at continuous rated power output at the Point of Interconnection at a power factor within the range of 0.95 leading to 0.95 lagging, unless Distribution the Transmission Provider has established different requirements that apply to all synchronous generators in the Control Area on a comparable basis. The requirements of this paragraph shall not apply to wind generators; rather, the requirements of Appendix H shall apply to wind generators.
Appears in 1 contract
Sources: Standard Large Generator Interconnection Agreement (Lgia)
Power Factor Design Criteria. Interconnection Customer shall design the Generating Facility to maintain a composite power delivery at continuous rated power output at the Point of Interconnection at a power factor within the range of 0.95 leading to 0.95 lagging, unless Distribution Provider has established different requirements that apply to all generators in the Control Area on a comparable basis. The requirements of this paragraph shall not apply to wind generators; rather, the requirements of Appendix H G shall apply to wind generators.
Appears in 1 contract
Power Factor Design Criteria. Interconnection Customer shall design the Large Generating Facility to maintain a composite power delivery at continuous rated power output at the Point of Interconnection at a power factor within the range of 0.95 leading to 0.95 lagging, unless Distribution Transmission Provider has established different requirements that apply to all generators in the Control Area on a comparable basis. The requirements of Appendix G to this paragraph shall not apply to wind generators; rather, the requirements of Appendix H LGIA shall apply to wind generators.
Appears in 1 contract
Sources: Standard Large Generator Interconnection Agreement (Lgia)
Power Factor Design Criteria. Interconnection Customer shall design the Generating Facility to maintain be capable of maintaining a composite power delivery at continuous rated power output at the Point of Interconnection at a all power factor within the range of factors over 0.95 leading to 0.95 lagging, unless Distribution Transmission Provider has established different requirements that apply to all generators in the Control Area on a comparable basis. The requirements of this paragraph shall not apply to wind generators; rather, the requirements of Appendix H shall apply to wind generators.established
Appears in 1 contract
Sources: Generator Interconnection Agreement
Power Factor Design Criteria. Interconnection Customer shall design the Large Generating Facility to maintain a composite power delivery at continuous rated power output at the Point of Interconnection at a power factor within the range of 0.95 leading to 0.95 lagging, unless Distribution Provider JPP has established different requirements that apply to all interconnected generators in the Control Area on a comparable basis. The requirements of this paragraph shall not apply to wind generators; rather, the requirements of Appendix H shall apply to wind generators.
Appears in 1 contract
Power Factor Design Criteria. Interconnection Customer shall design the Generating Facility to maintain a composite power delivery at continuous rated power output at the Point of Interconnection at a power factor within the minimum range of 0.95 leading to 0.95 lagging, unless Distribution Transmission Provider has established different requirements that apply to all generators in the Control Area Balancing Authority on a comparable basis. The Unless otherwise required by Applicable Laws and Regulations or Applicable Reliability Standards, the requirements of this paragraph shall not apply to wind generators; rather, the requirements of Appendix H shall apply to wind generators.
Appears in 1 contract
Sources: Transitional Cluster Generator Interconnection Agreement
Power Factor Design Criteria. Interconnection Customer shall design the Large Generating Facility to maintain a composite power delivery at continuous rated power output at the Point of Interconnection at a power factor within the range of 0.95 leading to 0.95 lagging, unless Distribution Transmission Provider has established different requirements that apply to all generators in the Control Area on a comparable basis. The requirements of this paragraph shall not apply to wind generators; rather, the requirements of Appendix H shall apply to wind generators.
Appears in 1 contract
Power Factor Design Criteria. Interconnection Customer shall design the Large Generating Facility to maintain a composite power delivery at continuous rated power output at the Point of Interconnection at a power factor within the range of of 0.95 leading to 0.95 lagging, unless Distribution Provider has established different requirements that apply to all generators in the Control Area on a comparable basis. The requirements of this paragraph shall not apply to wind generators; rather, the requirements of Appendix H shall apply to wind generators.
Appears in 1 contract
Sources: Clustering Large Generator Interconnection Agreement and Distribution Service Agreement