Dispatch and Scheduling 6.1.1 The SPD shall be entirely responsible to schedule its power as per the applicable regulations / requirements / guidelines of CERC / SERC /SLDC / RLDC or any other competent agency and same being recognized by the RLDC/SLDC or any other competent authority / agency as per applicable regulation/ law / direction and maintain compliance to the applicable Codes/ Grid Code requirements and directions, if any, as specified by concerned SLDC/RLDC from time to time. Any deviation from the schedule will attract the provisions of applicable regulation / guidelines / directions and any financial implication on account of this shall be on the account of the SPD. 6.1.2 The SPD shall be responsible for directly coordinating and dealing with the Buying Entity, State Load Dispatch Centres, Regional Power Committees, and other authorities in all respects in regard to declaration of availability, scheduling and dispatch of power and due compliance with deviation and settlement mechanism and the applicable Grid code Regulations, acknowledging that the SPD and Buying Entity are the Grid connected entities and SECI as an Intermediary Procurer/ trading licensee is not a Grid connected entity in respect of the power contracted under this Agreement. 6.1.3 The SPD shall be responsible for any deviation from scheduling and for any resultant liabilities on account of charges for deviation as per applicable regulations. UI charges on this account shall be directly paid by the SPD. 6.1.4 Auxiliary power consumption will be treated as per the concerned Central/State regulations. 6.1.5 Further, in case of any difference in scheduled energy at the interfaces of all the RLDCs concerned for the corridor of the power flow, including the RLDC of the Buying Entity, SECI will make payments corresponding to the lowest of the individual energy values to the SPD, until rectification of the above error.
Information Submission by Connecting Transmission Owner The initial information submission by Connecting Transmission Owner shall occur no later than one hundred eighty (180) Calendar Days prior to Trial Operation and shall include New York State Transmission System information necessary to allow the Developer to select equipment and meet any system protection and stability requirements, unless otherwise mutually agreed to by the Developer and Connecting Transmission Owner. On a monthly basis Connecting Transmission Owner shall provide Developer and NYISO a status report on the construction and installation of Connecting Transmission Owner’s Attachment Facilities and System Upgrade Facilities and System Deliverability Upgrades, including, but not limited to, the following information: (1) progress to date; (2) a description of the activities since the last report; (3) a description of the action items for the next period; and (4) the delivery status of equipment ordered.
Connecting Transmission Owner’s Attachment Facilities Construction The Connecting Transmission Owner’s Attachment Facilities shall be designed and constructed in accordance with Good Utility Practice. Upon request, within one hundred twenty (120) Calendar Days after the Commercial Operation Date, unless the Connecting Transmission Owner and Developer agree on another mutually acceptable deadline, the Connecting Transmission Owner shall deliver to the Developer “as-built” drawings, relay diagrams, information and documents for the Connecting Transmission Owner’s Attachment Facilities set forth in Appendix A. The Connecting Transmission Owner shall not transfer operational control of the Connecting Transmission Owner’s Attachment Facilities and Stand Alone System Upgrade Facilities to the NYISO upon completion of such facilities.
Connecting Transmission Owner’s Attachment Facilities Connecting Transmission Owner shall design, procure, construct, install, own and/or control the Connecting Transmission Owner’s Attachment Facilities described in Appendix A hereto, at the sole expense of the Developer.
CONNECTING TRANSMISSION OWNER’S INTERCONNECTION FACILITIES As depicted on the one-line diagram in Attachment 3, the Connecting Transmission Owner’s Interconnection Facilities consist of the following constructed or installed between the POI and PCO, as well as metering and telecommunications located at the ▇▇▇▇▇ Solar Collector Substation.