Precedence of Documentation. 1.5.1 If there is any inconsistency between the provisions of the body of this Contract and the Schedules, the body of this Contract shall take precedence. 1.5.2 Save in relation to derogations pursuant to clause 1.5.5, in the event of any inconsistency between Schedule 1 (Authority's Requirements) and Schedule 2 (Contractor's Proposals) or any documents produced in accordance with the provisions of this Contract (including the Initial Service Delivery Documents and the Service Delivery Documents), Schedule 1 (Authority's Requirements) shall take precedence. 1.5.3 In the event of any inconsistency between Schedule 13 (Authority Policies) and the other Schedules or any documents produced in accordance with the provisions of this Contract (including the Initial Service Delivery Documents and the Service Delivery Documents), Schedule 13 (Authority Policies) shall take precedence, save that where there is any conflict or inconsistency between Schedule 1 Part 2 (Authority’s Requirements) and Schedule 13 (Authority Policies), if the relevant part of Schedule 1 Part 2 (Authority’s Requirements) is listed as approved in Schedule 31 (Approved Specifications), such part of Schedule 1 Part 2 (Authority’s Requirements) shall take precedence. 1.5.4 The Authority may notify the Contractor of changes to the ‘approved’ status of any part of Schedule 1 Part 2 (Authority’s Requirements) as set out in Schedule 31 (Approved Specifications) from time to time in accordance with clause 84 (Notices). Such notifications shall not constitute a Change pursuant to clause 61 (Change to Custodial Service). 1.5.5 Any derogations from the requirements of Schedule 1 Part 2 (Authority’s Requirements) which are set out in Part D1 of Schedule 2 (Contractor’s Proposals) and/or from the Authority Policies which are set out in Appendix 2 to Schedule 2 (Contractor’s Proposals) and/or or which the Authority has approved in accordance with the provisions of Schedule 9 (Change Protocol) shall take precedence over the Authority Policies. For the avoidance of doubt, any request for such a derogation by the Contractor shall constitute a Contractor Change. 1.5.6 In the event of any inconsistency between Schedule 2 (Contractor’s Proposals) and the Initial Service Delivery Documents or the Service Delivery Documents, Schedule 2 (Contractor’s Proposals) shall take precedence.
Appears in 1 contract
Precedence of Documentation. 1.5.1 If there is any inconsistency between the provisions of the body of this Contract and the Schedules, the body of this Contract shall take precedence.
1.5.2 Save in relation to derogations pursuant to clause 1.5.5, in In the event of any inconsistency between Schedule 1 (Authority's Requirements) and Schedule 2 (Contractor's Proposals) or any documents produced in accordance with the provisions of this Contract (including the Initial Service Delivery Documents and the Service Delivery Documents), Schedule 1 (Authority's Requirements) shall take precedence.
1.5.3 In the event of any inconsistency between Schedule 13 12 (Authority Policies) and the other Schedules or any documents produced in accordance with the provisions of this Contract (including the Initial Service Delivery Documents and the Service Delivery Documents), Schedule 13 12 (Authority Policies) shall take precedence, save that where there is any conflict or inconsistency between Schedule 1 Part 2 1 ((Authority’s Requirements) (Custodial Service Specification)) and Schedule 13 12 (Authority Policies), if the relevant part of Schedule 1 Part 2 1 ((Authority’s Requirements) (Custodial Service Specification)) is listed as approved in Schedule 31 27 (Approved Specifications), such part of Schedule 1 Part 2 1 ((Authority’s Requirements) (Custodial Service Specification)) shall take precedence.
1.5.4 The Authority may notify the Contractor of changes to the ‘approved’ status of any part of Schedule 1 Part 2 1 (Authority’s Requirements) (Custodial Service Specification) as set out in Schedule 31 27 (Approved Specifications) from time to time in accordance with clause 84 (Notices). Such notifications shall not constitute a Change pursuant to clause 61 (Change to Custodial Service).
1.5.5 Any derogations from the requirements of Schedule 1 Part 2 (Authority’s Requirements) which are set out in Part D1 of Schedule 2 (Contractor’s Proposals) and/or from the Authority Policies which are set out in Appendix 2 to Schedule 2 (Contractor’s Proposals) and/or or which the Authority has approved in accordance with the provisions of Schedule 9 8 (Change Protocol) shall take precedence over the Authority Policies. For the avoidance of doubt, any request for such a derogation by the Contractor shall constitute a Contractor Change.
1.5.6 In the event of any inconsistency between Schedule 2 (Contractor’s Proposals) and the Initial Service Delivery Documents or the Service Delivery Documents, Schedule 2 (Contractor’s Proposals) shall take precedence.
1.5.7 In the event of any inconsistency between the provisions of this Contract (excluding the Controlled Documents) and any Controlled Document, the provisions of this Contract (excluding the Controlled Documents) shall take precedence.
Appears in 1 contract
Precedence of Documentation. 1.5.1 If there is any inconsistency between the provisions of the body of this Contract and the Schedules, the body of this Contract shall take precedence.
1.5.2 Save in relation to derogations pursuant to clause 1.5.5Error! Reference source not found., in the event of any inconsistency between Schedule 1 (Authority's Requirements) and Schedule 2 (Contractor's Proposals) or any documents produced in accordance with the provisions of this Contract (including the Initial Service Delivery Documents and the Service Delivery Documents), Schedule 1 (Authority's Requirements) shall take precedence.
1.5.3 In the event of any inconsistency between Schedule 13 (Authority Policies) and the other Schedules or any documents produced in accordance with the provisions of this Contract (including the Initial Service Delivery Documents and the Service Delivery Documents), Schedule 13 (Authority Policies) shall take precedence, save that where there is any conflict or inconsistency between Schedule 1 Part 2 (Authority’s Requirements) and Schedule 13 (Authority Policies), if the relevant part of Schedule 1 Part 2 (Authority’s Requirements) is listed as approved in Schedule 31 (Approved Specifications), such part of Schedule 1 Part 2 (Authority’s Requirements) shall take precedence.
1.5.4 The Authority may notify the Contractor of changes to the ‘approved’ status of any part of Schedule 1 Part 2 (Authority’s Requirements) as set out in Schedule 31 (Approved Specifications) from time to time in accordance with clause 84 (Notices). Such notifications shall not constitute a Change pursuant to clause 61 (Change to Custodial Service).
1.5.5 Any derogations from the requirements of Schedule 1 Part 2 (Authority’s Requirements) which are set out in Part D1 of Schedule 2 (Contractor’s Proposals) and/or from the Authority Policies which are set out in Appendix 2 to Schedule 2 (Contractor’s Proposals) and/or or which the Authority has approved in accordance with the provisions of Schedule 9 (Change Protocol) shall take precedence over the Authority Policies. For the avoidance of doubt, any request for such a derogation by the Contractor shall constitute a Contractor Change.
1.5.6 In the event of any inconsistency between Schedule 2 (Contractor’s Proposals) and the Initial Service Delivery Documents or the Service Delivery Documents, Schedule 2 (Contractor’s Proposals) shall take precedence.
Appears in 1 contract