Common use of Preconstruction Phase Clause in Contracts

Preconstruction Phase. 2.1.1 No later than twenty-one (21) days following receipt of Notice to Proceed with Preconstruction Services, attached hereto as Exhibit F, the CM/GC shall provide a preliminary evaluation of the Owner’s program, schedule, and construction budget requirements, each in terms of the other.

Appears in 4 contracts

Sources: Construction Manager / General Contractor Agreement, Construction Manager / General Contractor Agreement, Construction Manager / General Contractor Agreement

Preconstruction Phase. § 2.1.1 No later than twenty-one (21) days following receipt of Notice to Proceed with Preconstruction Services, attached hereto as Exhibit F, the CM/GC shall provide a preliminary evaluation of the Owner’s program, schedule, and construction budget requirements, each in terms of the other.

Appears in 2 contracts

Sources: Construction Manager / General Contractor Agreement, Construction Manager / General Contractor Agreement

Preconstruction Phase. § 2.1.1 No later than twenty-one (21) days following receipt of Notice to Proceed with Preconstruction Services, attached hereto as Exhibit F, the CM/GC shall provide a preliminary evaluation of the Owner’s program, schedule, schedule and construction budget requirements, each in terms of the other.

Appears in 1 contract

Sources: Construction Manager / General Contractor Agreement