Preliminary Pay Worksheet Clause Samples

Preliminary Pay Worksheet. Once each month that a progress payment is to be requested, the Contractor shall submit to A/E and ODR a complete, clean copy of a preliminary pay worksheet or preliminary pay application, to include the following: 10.2.1.1 Contractor’s estimate of the amount of Work performed, labor furnished and materials incorporated into the Work, using the established Schedule of Values; 10.2.1.2 An updated Work Progress Schedule including the executive summary and all required schedule reports; 10.2.1.3 HUB subcontracting plan Progress Assessment Report as required in Paragraph 4.2.5.1; 10.2.1.4 Such additional documentation as Owner may require as set forth in the elsewhere in the Contract Documents; and 10.2.1.5 Construction payment affidavit.
Preliminary Pay Worksheet. Once each month that a progress payment is to be requested, the Contractor shall submit to the A/E and the ODR a complete, clean copy of a preliminary pay worksheet or Preliminary Pay Application, to include the following: 10.2.1.1 The Contractor’s estimate of the amount of Work performed, labor furnished and materials incorporated into the Work, using the established Schedule of Values. 10.2.1.2 An updated Work Progress Schedule including the Executive Summary and all required schedule reports. 10.2.1.3 HUB Subcontracting Plan reports. 10.2.1.4 Such additional documentation as Owner may require as set forth elsewhere in the Contract Documents.
Preliminary Pay Worksheet once each month that a progress payment is to be requested, the CM-at-Risk shall submit to the Architect/Engineer and the ODR a complete, clean copy of a preliminary pay worksheet or Preliminary Pay Application, to include the following: 10.2.1.1 The CM-at-Risk’s estimate of the amount of Work performed, labor furnished and materials incorporated into the Work, using the established Schedule of Values. 10.2.1.2 An updated Work Progress Schedule including the Executive Summary and all required schedule reports. 10.2.1.3 Small Business Subcontracting Plan reports 10.2.1.4 Such additional documentation as Owner may require as set forth in the Supplementary General Conditions or elsewhere in the Contract Documents.
Preliminary Pay Worksheet. Once each month that a progress payment is to be requested, the Contractor shall submit to A/E and City a complete, clean copy of a preliminary pay worksheet or preliminary pay application, to include the following: 9.2.1.1 Contractor’s estimate of the amount of Work performed, labor furnished and materials incorporated into the Work, using the established Schedule of Values; 9.2.1.2 An updated Work Progress Schedule including the executive summary and all required schedule reports; 9.2.1.3 Such additional documentation as City may require as set forth in the Supplementary General Conditions or elsewhere in the Contract Documents; and
Preliminary Pay Worksheet. Once each month, the Contractor may submit to the Architect/Engineer and the ODR a complete, clean copy of a Preliminary Pay Worksheet, which shall attach the following: 1) The Contractor’s estimate of the amount of Work performed, labor furnished and materials incorporated into the Work, using the approved Schedule of Values; and 2) A schedule update as specified, an updated Submittal Schedule, invoices for stored materials and other supporting documentation, and such additional documentation as Owner may require and as otherwise specified.
Preliminary Pay Worksheet. Once each month that a progress payment is to be requested, the Contractor shall submit to Design Professional and OCM a complete, clean copy of a preliminary pay worksheet or preliminary pay application, to include the following: 13.2.1.1 Contractor’s estimate of the amount of Work performed, labor furnished, and materials incorporated into the Work, using the established Schedule of Values; 13.2.1.2 An updated Work Progress Schedule including the executive summary and all required schedule reports; 13.2.1.3 HUB subcontracting plan Progress Assessment Report; 13.2.1.4 Reimbursable expenses incurred solely and directly in support of the Project within one of the following categories:  Travel expenditures at State of Texas reimbursement rates, provided that reimbursement will not be granted for travel 1) within the Denton-Dallas-Fort Worth metroplex or 2) involving less than 150 miles round-trip; or  Reproductions, printing, printing supplies, plotting, photographs, renderings, postage, binding, collating, delivery and handling of reports; Drawings and Specifications or other project-related work product other than that used solely in-house by Contractor at actual expense incurred; or  Fees and associated reimbursable expenses paid to Consultants hired in accordance with prior written approval from Owner. 13.2.1.5 Such additional documentation as Owner may require in the Contract Documents; and 13.2.1.6 Construction payment affidavit.
Preliminary Pay Worksheet. Once each month that a progress payment is to be requested, the Contractor shall submit to A/E and ODR a complete, clean copy of a preliminary pay worksheet or preliminary pay application, to include the following: 9.2.1.1 Contractor’s estimate of the amount of Work performed, labor furnished and materials incorporated into the Work, using the established Schedule of Values; 9.2.1.2 An updated Work Progress Schedule including the executive summary and all required schedule reports; 9.2.1.3 Such additional documentation as Owner may require as set forth in the elsewhere in the Contract Documents; and 9.2.1.4 Construction payment affidavit. Payment affidavit such as AIA G706, or approved equal, shall be submitted with each pay application request.

Related to Preliminary Pay Worksheet

  • Preliminary Evaluation Site evaluation and planning functions should proceed concurrently with the accomplishment of Schematic Design, Design Development, and Construction Documents. The Design Professional shall conduct a preliminary review of the site based on information furnished by the Owner and any other information that is obtained by the Design Professional. The Design Professional will advise the Owner of potential site-related problems that the Design Professional notes from such review.

  • Preliminary 1. Short title

  • Preliminary Design § 4.3.1 Upon the Owner’s issuance of a written consent to proceed under Section 4.2.3, the Design-Builder shall prepare and submit a Preliminary Design to the Owner. The Preliminary Design shall include a report identifying any deviations from the Owner’s Criteria, and shall include the following: .1 Confirmation of the allocations of program functions; .2 Site plan; .3 Building plans, sections and elevations;

  • Preliminary Design Phase 30 percent plans) A. Proceed with Preliminary Design Phase after the completion of the Conceptual phase which includes: Acceptance by Owner of the Conceptual Report and any other Study and Report Phase deliverables; selection by Owner of a recommended solution; issuance by Owner of any instructions for use of Project Strategies, Technologies, and Techniques, or for inclusion of sustainable features in the design, and Indication by Owner of any specific modifications or changes in the scope, extent, character, or design requirements of the Project desired by Owner. 1. Prepare Preliminary Design Phase documents consisting of final design criteria, preliminary drawings, outline specifications, and written descriptions of the Project. 2. Include on plans, property lines, structure locations, ownership names and contact information. 3. In preparing the Preliminary Design Phase documents, use any specific applicable Project Strategies, Technologies, and Techniques authorized by Owner during or following the Study and Conceptual Phase, and include sustainable features, as appropriate, pursuant to Owner’s instructions. 4. Provide necessary field surveys, topographic and utility mapping for Engineer’s design purposes. Comply with the scope of work and procedure for the identification and mapping of existing utilities as defined by Section A1.03 “Utility Requirements” and Section A1.04 “Survey Services” 5. Visit the Site as needed to prepare the Preliminary Design Phase documents. 6. Advise Owner if additional reports, data, information, or services of the types described are necessary and assist Owner in obtaining such reports, data, information, or services. 7. Continue to assist Owner with Project Strategies, Technologies, and Techniques that Owner has chosen to implement. 8. Based on the information contained in the Preliminary Design Phase documents, prepare a revised opinion of probable Construction Cost, and assist Owner in tabulating the various cost categories which comprise Total Project Costs. 9. Obtain and review Owner’s instructions regarding Owner’s procurement of construction services (including instructions regarding advertisements for bids, instructions to bidders, and requests for proposals, as applicable), Owner’s construction contract practices and requirements, insurance and bonding requirements, electronic transmittals during construction, and other information necessary for the finalization of Owner’s bidding-related documents (or requests for proposals or other construction procurement documents), and Construction Contract Documents. Also obtain and review copies of Owner’s design and construction standards, Owner’s standard forms, general conditions, supplementary conditions, text, and related documents or content for Engineer to include in the draft bidding-related documents (or requests for proposals or other construction procurement documents), and in the draft Construction Contract Documents, when applicable. 10. Development communication plan for project: considering the use of door hangers, letters, public meetings, changeable message boards. 11. Furnish 6 review copies of the Preliminary Design Phase documents, opinion of probable Construction Cost, and any other Preliminary Design Phase deliverables to Owner by established due date, and review them with Owner. Owner shall submit to Engineer any comments regarding the furnished items. 12. Revise the Preliminary Design Phase documents, opinion of probable Construction Cost, and any other Preliminary Design Phase deliverables in response to Owner’s comments, as appropriate, and furnish to Owner 6 copies of the revised Preliminary Design Phase documents, revised opinion of probable Construction Cost, and any other deliverables by the specified due date. 13. Engineer’s services under the Preliminary Design Phase will be considered complete on the date when Engineer has delivered to Owner the revised Preliminary Design Phase documents, revised opinion of probable Construction Cost, and any other Preliminary Design Phase deliverables.