Preliminary Work. 1. Confirm property line dimensions of the Project Site from survey. No work shall be performed outside the property line. Install a fence complying with Laws around the exterior of the site. 2. All utilities (including electricity, gas, water, and sewer, and fire hydrants) shall be disconnected before any removal and/or demolition activity is commenced. Removal of utilities shall be conducted by licensed persons and in all cases in compliance with, and as required by, Law. 3. Provide protection for any neighboring structures or improvements within ten (10) feet of the property line on any side or as otherwise required by Law. Protection of adjacent properties shall include protection from debris, dust, and excessive noise. All work shall be wet down periodically as necessary to minimize dust. 4. If asbestos is present, comply with Section C below. 5. If an in-ground or underground tank is present or if there are propane tanks on the site, comply with Section D below. 6. Obtain, at Contractor’s expense, all permits and approvals required by Code and Environmental Laws (if applicable) for the demolition of the Project. 7. Prepare and send to Owner a written implementation plan (a “Demo Plan”) describing briefly but in sufficient detail the proposed means and methods for proceeding with the demolition in accordance with these Demolition Specifications. Include in the Demo Plan any features of the existing structure requiring special means and methods which would not be covered in the conventional demolition of a one or two story residence. Include in the Demo Plan a list of all permits and approvals obtained pursuant to paragraph 6 above. State in the Demo Plan whether (a) there is asbestos which must be remediated (and, if so, how Contractor will comply with Section C below) and (b) whether there is an underground tank (or tanks) on the Project Site (and, if so, how Contractor will comply with Section D below). 8. If, within fifteen (15) days after Owner receives the Demo Plan, Owner does not give notice to Contractor requiring a modification of the Demo Plan, or requiring actions to be taken with respect to the Demo Plan, Contractor may give notice to Owner of its intent to proceed under the Demo Plan. If, within five (5) days after Owner receives such notice, Owner does not give notice to Contractor requiring a modification of the Demo Plan, or requiring actions to be taken with respect to the Demo Plan, Contractor shall proceed with demolition in accordance with the Demolition Specification in compliance with this Demolition Agreement and in accordance with the Demo Plan. 9. If, within the timeframe specified in paragraph 8 above, Owner gives notice to Contractor requiring a modification of the Demo Plan, or requiring actions to be taken with respect to the Demo Plan, Contractor shall modify the Demo Plan and/or take the required actions, and resubmit the Demo Plan to Owner. The resubmitted Demo Plan shall then be treated as if it were an initial submission of the Demo Plan under these paragraphs 8 and 9. 10. Contractor shall provide the services of a licensed engineer, at Contractor’s expense, to review and accept these Demolition Specifications, to sign and seal (if applicable) all necessary filings; and to perform all tests, reviews, inspections, sign-offs, and other matters under this Demolition Specification or otherwise in the performance of the Work which by Law require action or signature of a licensed engineer.
Appears in 2 contracts
Sources: Demolition Agreement, Demolition Agreement
Preliminary Work. 1. Confirm property line dimensions of the Project Site from survey. No work shall be performed outside the property line. Install a fence complying with Laws around the exterior of the site.
2. All utilities (including electricityAs applicable, gas, water, connected water and sewer, and fire hydrants) sewer shall be disconnected before any removal and/or demolition activity is commenced. Removal of utilities shall be conducted by a licensed persons and person an in all cases in compliance with, and as required by, Law.
3. Provide protection for any neighboring structures or improvements within ten (10) feet of the property line on any side or as otherwise required by Law. Protection of adjacent properties shall include protection from debris, dust, and excessive noise. All work shall be wet down periodically as necessary to minimize dust.
43. If asbestos is present, comply with Section C below.
54. If an in-ground or underground tank is present or if there are propane tanks on the site, comply with Section D below.
65. Obtain, at Contractor’s expense, all permits and approvals required by Code and Environmental Laws (if applicable) for the demolition of the Project.
76. Prepare and send to Owner HTFC a written implementation plan (a “Demo Plan”) describing briefly but in sufficient detail the proposed means and methods for proceeding with the demolition in accordance with these Demolition Specifications. Include in the Demo Plan any features of the existing structure requiring special means and methods which would not be covered in the conventional demolition of a one or two story residence. Include in the Demo Plan a list of all permits and approvals obtained pursuant to paragraph 6 above. State in the Demo Plan whether (a) there is asbestos which must be remediated (and, if so, how Contractor will comply with Section C below) and (b) whether there is an underground tank (or tanks) on the Project Site (and, if so, how Contractor will comply with Section D below).
87. If, within fifteen (15) days after Owner HTFC receives the Demo Plan, Owner HTFC does not give notice to Contractor requiring a modification of the Demo Plan, or requiring actions to be taken with respect to the Demo Plan, Contractor may give notice to Owner HTFC of its intent to proceed under the Demo Plan. If, within five (5) days after Owner HTFC receives such notice, Owner HTFC does not give notice to Contractor requiring a modification of the Demo Plan, or requiring actions to be taken with respect to the Demo Plan, Contractor shall proceed with demolition in accordance with the Demolition Specification in compliance with this Demolition Agreement and in accordance with the Demo Plan.
98. If, within the timeframe specified in paragraph 8 above, Owner HTFC gives notice to Contractor requiring a modification of the Demo Plan, or requiring actions to be taken with respect to the Demo Plan, Contractor shall modify the Demo Plan and/or take the required actions, and resubmit the Demo Plan to OwnerHTFC. The resubmitted Demo Plan shall then be treated as if it were an initial submission of the Demo Plan under these paragraphs 8 and 9.
10. Contractor shall provide the services of a licensed engineer, at Contractor’s expense, to review and accept these Demolition Specifications, to sign and seal (if applicable) all necessary filings; and to perform all tests, reviews, inspections, sign-offs, and other matters under this Demolition Specification or otherwise in the performance of the Work which by Law require action or signature of a licensed engineer.