Prerequisites for Final Acceptance. After the issuance of a Certificate of Agency Use and Occupancy for the entire Work and after the CM has completed all of the Work required by this Contract, including Change Orders and Punch List Items, the CM shall submit the following completed items to DCAMM together with such additional items as may be specified in the Contract Documents: (1) A completed Final Application for Payment showing a final accounting of all changes in the Work, on the form provided by DCAMM; (2) Certification and satisfactory evidence that all taxes, fees, and similar obligations have been paid; (3) Consent of the Surety to Final Payment executed by applicable bonding companies. Certified copy of the Punch List stating that the CM has completed or corrected every item listed. (4) Evidence of CM's continuing Completed Operations Insurance coverage to the extent required by the Contract Documents. (5) All final record Drawings and documents in the forms specified by the Contract Documents. (6) A notarized certification that all purchases made under the tax exemption certificate were legitimate and entitled to exemption. (7) Written certifications from the Department of Public Safety and the Designer to the effect that: a) the Work has been inspected for compliance with the Contract Documents and has satisfied the Department of Public Safety; b) all equipment and systems included in the Work have been tested in the presence of the Designer and are operational and satisfactory; c) the Work is completed and ready for final inspection. (8) Such other items as may be required by the Contract Documents.
Appears in 2 contracts
Sources: Construction Manager at Risk Services Agreement, Construction Manager at Risk Services Agreement
Prerequisites for Final Acceptance. After the issuance of a Certificate of Agency Use and Occupancy for the entire Work Work, and after the CM Contractor has completed all of the Work required by this Contract, including Change Orders and Punch List Items, the CM Contractor shall submit the following completed items to DCAMM the Town together with such additional items as may be specified in the Contract Documents:
(1) A completed Final Application for Payment showing a final accounting of all changes in the Work, on the form provided by DCAMM;the Town.
(2) Certification and satisfactory evidence that all taxes, fees, and similar obligations have been paid;.
(3) Consent of the Surety to Final Payment executed by applicable bonding companies. .
(4) Certified copy of the Punch List stating that the CM Contractor has completed or corrected every item listed.
(45) Evidence of CMContractor's continuing Completed Operations Insurance coverage to the extent required by the Contract Documents.
(56) All final record Drawings and documents in the forms specified by the Contract Documents.
(67) A notarized certification that all purchases made under the tax exemption certificate were legitimate and entitled to exemption.
(7) 8) Written certifications from the Department of Public Safety building department and the Designer to the effect that: :
a) the Work has been inspected for compliance with the Contract Documents and has satisfied the Department of Public Safetybuilding department; b) all equipment and systems included in the Work have been tested in the presence of the Designer and are operational and satisfactory; c) the Work is completed and ready for final inspection.
(8) 9) Such other items as may be required by the Contract Documents.
Appears in 1 contract
Sources: Owner Contractor Agreement
Prerequisites for Final Acceptance. After the issuance of a Certificate of Agency Use and Occupancy for the entire Work and after the CM Contractor has completed all of the Work required by this Contract, including Change Orders and Punch List Items, the CM Contractor shall submit the following completed items to DCAMM the DCR together with such additional items as may be specified in the Contract Documents:
(1) A completed Final Application final request for Payment payment showing a final accounting of all changes in the Work, on the form provided by DCAMM;.
(2) Certification and satisfactory evidence that all taxes, fees, and similar obligations have been paid;.
(3) Consent of the Surety to Final Payment executed by applicable bonding companies. .
(4) Certified copy of the Punch List stating that the CM Contractor has completed or corrected every item listed.
(45) Evidence of CMthe Contractor's continuing Completed Operations Insurance coverage to the extent required by the Contract Documents.
(56) All final record Drawings and documents in the forms specified by the Contract Documents.
(67) A notarized certification that all purchases made under the tax exemption certificate were legitimate and entitled to exemption.
(7) 8) Written certifications from the Department of Public Safety and and/or the Designer DCR, where required, to the effect that: a) the Work has been inspected for compliance with the Contract Documents and has satisfied the Department of Public Safety; b) all equipment and systems included in the Work have been tested in the presence of the Designer DCR and are operational and satisfactory; c) the Work is completed and ready for final inspection.
(8) 9) Such other items as may be required by the Contract Documents.
Appears in 1 contract
Sources: Construction Contract
Prerequisites for Final Acceptance. After the issuance of a Certificate of Agency Use and Occupancy Substantial Completion for the entire Work and after the CM has completed all of the Work required by this Contract, including Change Orders and Punch List Itemsitems, the CM shall submit the following completed items to DCAMM together with such additional items as may be specified in the Contract Documents:
(1) A completed Final Application final application for Payment payment showing a final accounting of all changes in the Work, on the form provided by DCAMM;
(2) Certification and satisfactory evidence that all taxes, fees, and similar obligations have been paid;
(3) Consent of the Surety CM’s surety to Final Payment final payment executed by applicable bonding companies. .
(4) Certified copy of the Punch List stating that the CM has completed or corrected every item listed.
(45) Evidence of CM's continuing Completed Operations Insurance completed operations insurance coverage to the extent required by the Contract Documents.
(56) All final record Drawings and documents in the forms specified by the Contract Documents.
(67) A notarized certification that all purchases made under the tax exemption certificate were legitimate and entitled to exemption.
(7) 8) Written certifications from the Department of Public Safety and the Designer to the effect that: a) the Work has been inspected for compliance with the Contract Documents and has satisfied the Department of Public Safety; b) all equipment and systems included in the Work have been tested in the presence of the Designer and are operational and satisfactory; c) the Work is completed and ready for final inspection.
(8) 9) Such other items as may be required by the Contract Documents.. For DCAMM Use Only