Priority of Work. The CZS shall have the right to decide the time, order and priority in which the various portions of the Work shall be performed and all other matters relative to the timely and orderly conduct of the Contractor’s Work. CZS’s rights herein shall in no way relieve the Contractor of its responsibility to control and coordinate the Work and provide a safe worksite. The Contractor shall commence its work when notified to proceed by the CZS and if such work is interrupted for any reason the Contractor shall resume such work within two working days from the CZS’s notice to do so.