Common use of Procedure for Relief and Compensation Clause in Contracts

Procedure for Relief and Compensation. then the Contractor shall not be entitled to any extension of time, compensation, or relief from its obligations under the Contract in respect of the period for which the information is delayed.

Appears in 3 contracts

Sources: Agreement for Islington Hra Pfi Street Properties, Agreement for Islington Hra Pfi Street Properties, Agreement for Islington Hra Pfi Street Properties

Procedure for Relief and Compensation. then the Contractor shall not be entitled to any extension of time, compensation, compensation or relief from its obligations under the Contract this Agreement in respect of the period for which the information is delayed.

Appears in 1 contract

Sources: Project Agreement