Procedure for Relief and Compensation. Subject to Clause 15.8 (Late Provision of Information) to obtain relief and/or claim compensation the Contractor must:- 15.6.1 as soon as practicable, and in any event within fifteen (15) Working Days after it became aware that the Compensation Event has caused or is likely to cause delay, breach of an obligation under this Contract and/or the Contractor to incur costs or lose revenue, give to the Authority a notice of its claim for an extension of time to the Relevant Date, payment of compensation and/or relief from its obligations under the Contract; 15.6.2 within ten (10) Working Days of receipt by the Authority of the notice referred to in Clause 15.6.1 above, give full details of the Compensation Event and the extension of time to the Relevant Date and/or any Estimated Change in Project Costs and/or loss of revenue claimed;