Procedure for Relief and Compensation. Subject to clause 15.4 (Late Provision of Notice or Information), to obtain relief, extension and/or claim compensation, the Contractor must: 15.2.1 as soon as practicable, and in any event within twenty (20) Business Days, after it became aware that the Compensation Event has caused or is likely to cause delay, breach of an obligation under this Contract and/or the Contractor to incur costs, (or if earlier after it has received written notice from the Authority's Representative that a Compensation Event has occurred and that expressly requires the Contractor to claim relief, extension and/or compensation pursuant to this clause 15.2) give to the Authority a notice of its claim for: 15.2.1.1 an extension of time to (as appropriate): (a) the Services Commencement Date; (b) any date specified in a RRAPP Band Deactivation Notice for an increase in the number of Available Prisoner Places; (c) any date specified in a RRAPP Band Activation Notice for the reduction in the number of Available Prisoner Places; and/or (d) the period specified in paragraph (i) of the definition of Contractor Default; and/or 15.2.1. 2 payment of compensation; and/or
Appears in 1 contract
Procedure for Relief and Compensation. Subject to clause 15.4 (Late Provision of Notice or Information), to obtain relief, extension and/or claim compensation, the Contractor must:
15.2.1 as soon as practicable, and in any event within twenty (20) Business Days, Days after it became aware that the Compensation Event has caused or is likely to cause delay, breach of an obligation under this Contract and/or the Contractor to incur costs, (or if earlier after it has received written notice from the Authority's Representative that a Compensation Event has occurred and that expressly requires the Contractor to claim relief, extension and/or compensation pursuant to this clause 15.2) give to the Authority a notice of its claim for:
15.2.1.1 an extension of time to (as appropriate):
(a) the Services Commencement Date;
(b) any date specified in a RRAPP Band Deactivation Notice for an increase in the number of Available Prisoner Places;
(c) any date specified in a RRAPP Band Activation Notice for the reduction in the number of Available Prisoner Places; and/or
(d) the period specified in paragraph (i) of the definition of Contractor Default; and/or
15.2.1. 2 payment of compensation; and/or
Appears in 1 contract