Common use of Programme of Works Clause in Contracts

Programme of Works. 18.1 The Contractor shall, within the period stated in the appendix to these conditions, submit for the approval of the Architect a programme of Works in such form and detail as the Architect shall reasonably prescribe. 18.2 Should actual progress not match the programme, the Contractor shall amend the programme accordingly and submit the revisions to the Architect. In the event that a Contractor fails to submit or amend a programme within a reasonable time after being so instructed by the Architect, the Employer may withhold half of the amount due to the Contractor in subsequent payment certificates until the default is rectified. 18.3 Neither the submission of the programme by the Contractor nor its approval by the Architect shall in any way relieve the Contractor from any of his duties and obligations under the contract.

Appears in 2 contracts

Sources: Building Works Contract, Building Works Contract