Programming. A. A project scope statement will be supplied by CDB for projects with a simple or well-defined scope. The scope may contain background and justification for the project and quantification of work items contained in the project. The project scope statement will define the project budget. B. For new construction and major rehabilitation projects, CDB may provide a program statement describing proposed program activities, space requirements, and equipment needs. C. In the event a program statement is not provided by CDB and programming is required from the A/E, it will be considered as an additional service with compensation negotiated.
Appears in 6 contracts
Sources: Professional Services, Professional Services, Professional Services
Programming. A. A project scope statement will be supplied by CDB for projects with a simple or well-defined scopethis project. The scope may contain background and justification for the project and quantification of work items contained in the project. The project scope statement will define the project budget.
B. For new construction and major rehabilitation projects, CDB may provide a program statement describing proposed program activities, space requirements, and equipment needs.
C. In the event a program statement is not provided by CDB and programming is required from the A/E, it will be considered as an additional service with compensation negotiated.
Appears in 4 contracts
Sources: Construction Management Services Agreement, Construction Management Services Agreement, Construction Management Services Agreement
Programming. A. A project scope statement will be supplied by CDB for projects with a simple or well-well- defined scope. The scope may contain background and justification for the project and quantification of work items contained in the project. The project scope statement will define the project budget.
B. For new construction and major rehabilitation projects, CDB may provide a program statement describing proposed program activities, space requirements, and equipment needs.
C. In the event a program statement is not provided by CDB and programming is required from the A/E, it will be considered as an additional service with compensation negotiated.
Appears in 2 contracts
Sources: Professional Services, Professional Services
Programming. A. A project scope statement will be supplied by CDB for projects with a simple or well-defined scope. The scope may contain background and justification for the project and quantification of work items contained in the project. The project scope statement will define the project budget.
B. For new construction and major rehabilitation projects, CDB may provide a program statement describing proposed program activities, space requirements, and equipment needs.
C. 1. In the event a program statement is not provided by CDB and programming is required from the A/E, it will be considered as an additional service with compensation negotiated.
Appears in 2 contracts
Sources: Professional Services Agreement, Professional Services Agreement