Progress Documentation Clause Samples

Progress Documentation. Service Provider shall provide District progress reports in a format and on a schedule as District directs. Progress reports shall include a description of work completed, cumulative dollar costs incurred, anticipated work for the next reporting period, percentage of work complete, and the expected completion date for remaining work. The report shall identify problem areas and important issues that may affect project cost and/or schedule. The report shall present actual percent completion versus planned percent completion.
Progress Documentation. Design Professional shall provide District progress reports in a format and on a schedule as District directs. Progress reports shall include a description of work completed, cumulative dollar costs incurred, anticipated work for the next reporting period, percentage of work complete, and the expected completion date for remaining work. The report shall identify problem areas and important issues that may affect project cost and/or schedule. The report shall present actual percent completion versus planned percent completion.
Progress Documentation. Service Provider shall provide District progress reports as described in Deliverables section of Attachment A, Scope of Services.

Related to Progress Documentation

  • Project Documentation All documentation provided to the City other than Project drawings shall be furnished on a Microsoft compatible compact disc.

  • Licensed Documentation If commercially available, Licensee shall have the option to require the Contractor to deliver, at Contractor’s expense: (i) one (1) hard copy and one (1) master electronic copy of the Documentation in a mutually agreeable format; (ii) based on hard copy instructions for access by downloading from the Internet

  • Technical Documentation Prior to commencement of the Tests on Completion, the Contractor shall supply to the Engineer the technical documentation as specified in the Employer’s Requirements. The Works or Section shall not be considered to be completed for the purposes of taking- over under sub-clause 10.1 [Taking Over of the Works and Sections] until the Engineer has received the technical documentation as defined in this sub-clause 5.7, the "history file" including design calculations and certain certification as well as any other documents required to meet the CE Marking requirements.

  • Product Documentation You should review the policy documents carefully to ensure they accurately reflect the cover, conditions, limits and other terms that you require. Particular attention should be paid to policy conditions and warranties as failure to comply with these could invalidate your policy. Claims can arise, under certain types of insurance contract, long after the expiry of the policy. It is therefore important that you retain and keep safely all documents associated with your policy.

  • Project Implementation The Borrower shall: