Progress Payment Application Sample Clauses

A Progress Payment Application clause outlines the process by which a contractor or service provider requests interim payments for work completed during a project. Typically, this clause specifies the timing, format, and required documentation for submitting payment applications, such as invoices or progress reports, and may set out the approval process by the client or project manager. Its core function is to ensure that payments are made incrementally as work progresses, providing financial stability to the contractor and aligning payments with actual project milestones or deliverables.
POPULAR SAMPLE Copied 1 times
Progress Payment Application. The Contractor shall input the established amounts into a master spreadsheet and then prepare a Progress Payment Application for the payment period. The payment application will include only those Offsite Costs, Direct Costs and Indirect Costs that County and Contractor agree are properly due and owing based on the status of the Work.
Progress Payment Application. The Contractor shall certify in the Progress Payment Application that the portion of the Work for which payment is requested has been satisfactorily completed and/or that any materials specified in the Progress Payment Application not already incorporated into the Project are stored where indicated.
Progress Payment Application. The form that is accepted by ▇▇▇▇▇▇▇ and used by CM@R is requesting progress payments or final payment and which will include such supporting documentation as is required by the Contract Documents and/or ▇▇▇▇▇▇▇.

Related to Progress Payment Application

  • PROGRESS PAYMENT ‌ 9.2.1 City shall retain five percent (5%) of the undisputed amount due on each progress payment, or the percentage stated in the Notice Inviting Bids, whichever is greater, as retention to ensure full and complete performance of the Work. Subject to City’s right of withholding under Paragraph 9.4.2 of these General Conditions, City agrees to pay to Contractor within thirty (30) Days of receipt of a properly submitted Application for Payment an amount equal to ninety-five percent (95%), or a lesser amount if corresponding to a higher retention percentage, if applicable, of the sum of the following, excepting therefrom any amounts which are disputed by City: (i) Construction Manager’s determination of the value, expressed as a percentage of the Contract Sum, of the Work in permanent place that has been tested and accepted as of the end of the preceding month. (ii) Construction Manager’s determination of the value of materials suitably stored but not yet incorporated into the Work, subject to Paragraph 9.3.6 of these General Conditions. (iii) Less amounts previously paid. 9.2.2 At any Time after fifty percent (50%) of the Work has been determined by Construction Manager to be completed, City may in its sole discretion, make any of the remaining progress payments in accordance with the calculation in Paragraph 9.2.1 of these General Conditions based on one hundred percent (100%) of City’s determination of the value of the Work in place and of stored materials not yet incorporated into the Work. 9.2.3 Progress payments shall not be construed as City's Acceptance of any or all of the Work and shall not be a waiver of any or all rights City has under the Contract Documents.

  • Progress Payments 9.5.1 After the Architect has issued a Certificate for Payment, the State shall make payment in the manner and within the time provided in the Contract Documents. 9.5.2 The Contractor shall promptly pay each Subcontractor, upon receipt of payment from the State, out of the amount paid to the Contractor on account of such Subcontractor's Work, the amount to which said Subcontractor is entitled, reflecting the percentage actually retained, if any, from payments to the Contractor on account of such Subcontractor's Work. The Contractor shall, by an appropriate agreement with each Subcontractor, require each Subcontractor to make payments to his or her Sub-subcontractors in similar manner. 9.5.3 The Architect may, on request and at his discretion, furnish to any Subcontractor, if practicable, information regarding the percentages of completion or the amounts applied for by the Contractor and the action taken thereon by the Architect on account of Work done by such Subcontractor. 9.5.4 Neither the State nor the Architect shall have any obligation to pay or to see to the payment of any moneys to any Subcontractor. 9.5.5 No Certificate for a progress payment, nor any progress payment, nor any partial or entire use or occupancy of the Project by the State, shall constitute an acceptance of any Work not in accordance with the Contract Documents.

  • Progress Payments; Retainage A. Owner shall make progress payments on account of the Contract Price on the basis of Contractor’s Applications for Payment on the third Wednesday of the Month during performance of the Work as provided in Paragraph 6.02.A.1 below, provided that such Applications for Payment have been submitted in a timely manner and otherwise meet the requirements of the Contract. All such payments will be measured by the Schedule of Values established as provided in the General Conditions (and in the case of Unit Price Work based on the number of units completed) or, in the event there is no Schedule of Values, as provided elsewhere in the Contract. 1. Prior to Substantial Completion, progress payments will be made in an amount equal to the percentage indicated below but, in each case, less the aggregate of payments previously made and less such amounts as Owner may withhold, including but not limited to liquidated damages, in accordance with the Contract a. 95 percent of Work completed (with the balance being retainage). If the Work has been 50 percent completed as determined by Engineer, and if the character and progress of the Work have been satisfactory to Owner and Engineer, then as long as the character and progress of the Work remain satisfactory to Owner and Engineer, there will be no additional retainage; and

  • Application for Payment The form acceptable to Owner that is to be used by the Contractor during the course of the Work in requesting payment from the Owner and that is to be accompanied by such supporting documentation as is required by the Contract Documents.

  • Applications for Payment 9.3.1 At least ten days before the date for each progress payment established in the State- Contractor Agreement, the Contractor shall submit to the Architect an itemized Application for Payment, notarized if required, supported by such data substantiating the Contractor's right to payment as the State or the Architect may require. The application for payment must, at a minimum, reflect retainage and the required waivers of lien and any other support documentation enumerated elsewhere in the Contract Documents. 9.3.2 Unless otherwise provided in the Contract Documents, payments will be made on account of materials or equipment not incorporated in the Work but delivered and suitably stored at the site and, if approved in advance by the State, payments may similarly be made for materials or equipment suitably stored at some other location agreed upon in writing. Payments for materials or equipment stored on or off the site shall be conditioned upon submission by the Contractor of bills of sale or such other procedures satisfactory to the State to establish the State's title to such materials or equipment or otherwise protect the State's interest, including applicable insurance and transportation to the site for those materials and equipment stored off the site. 9.3.3 The Contractor warrants that title to all Work, materials and equipment covered by an Application for Payment will pass to the State either by incorporation in the construction or upon the receipt of payment by the Contractor, whichever occurs first, free and clear of all liens, claims, security interests or encumbrances, hereinafter referred to in this Article 9 as "liens"; and that no Work, materials or equipment covered by an Application for Payment will have been acquired by the Contractor, or by any other person performing Work at the site or furnishing materials and equipment for the Project, subject to an agreement under which an interest therein or an encumbrance thereon is retained by the seller or otherwise imposed by the Contractor or such other person.