PROGRESS SCHEDULE. a) The Contractor shall submit to the Director of Works for his approval a Progress Schedule within one week of the signing of the Contract. b) The Progress Schedule shall show the sequence of the Works and the dates by which the Contractor proposes to complete the various phases of the Work. c) One copy of the Progress Schedule shall be kept on Site at all times and the actual progress of the various phases of the work shall be entered thereon at intervals of not more than seven (7) calendar days. d) No changes shall be made to the Progress Schedule without the written approval of the Director of Works.