Project Close-out. The Consultant shall make final review of construction to determine if work was completed in general conformance of the construction contract documents; assist in the preparation of final “punch list” when the project is substantially completed; assist in negotiating the final payment for construction; and submit a final letter report upon which final settlement and contract closeout can be based. If required, prepare and submit to Florida Department of Environmental Protection (FDEP) or Department of Health for approval, the FDEP certificate of completion of construction for both water and sewer.