Project Milestone. Supplier's major equipment shall be delivered to the Generating Facility's construction site. Completion Date: Sixteen (16) months after Notice to Proceed has been issued to the construction contractor under the EPC Contract.
Appears in 2 contracts
Sources: Development Loan Agreement (Nevada Geothermal Power Inc), Development Loan Agreement (Nevada Geothermal Power Inc)
Project Milestone. Supplier's major equipment shall be delivered to the Generating Facility's construction site. Completion Date: Sixteen (16) Two months after Notice to Proceed has been issued to the construction contractor under the EPC Contract, defined in Milestone D above (or thirteen (13) months after AA).
Appears in 1 contract
Project Milestone. Supplier's major equipment shall be delivered to the Generating Facility's construction site. site Completion Date: Sixteen (16) -3 months after Notice to Proceed has been issued to the construction contractor under the EPC ContractAA.
Appears in 1 contract