Project Schedule Updates. Construction Manager shall update the Project Schedule (including a two-week look-ahead schedule) on a regular basis, but not less than one (1) time per month to assure maximum utilization of all Trade Contractors. All revisions and updates to the Project Schedule shall be approved by Owner.

Appears in 2 contracts

Sources: Construction Management Agreement (New York Times Co), Construction Management Agreement (New York Times Co)